[ RadSafe ] Nuclear industry may running out of steam
Sandy Perle
sandyfl at cox.net
Mon Nov 26 10:34:35 CST 2007
Note: sent this yesterday but I did not see that it was sent:
Interesting perspective. I suppose the theory is that if there aren't a
number of new plants planned to meet their speculated number to be
considered a "renaissance", then this doesn't exist. Compared to the number
of plants evaluated since TMI, the current situation for new NPPs is more
then a renaissance! The following is a list of just the plants being
considered in the USA posted by the Nuclear Energy Institute (NEI):
New Nuclear Plant Status
Company
Site(s)
Design, # of Units
Early Site Permit (ESP)
Construction / Operating License Submittal
Alternate Energy Holdings
Bruneau, ID
EPR
-
FY 2009
Amarillo Power
Vicinity of Amarillo, TX
EPR
-
FY 2009
AmerenUE
Callaway, MO
EPR
-
FY 2008
Constellation (UniStar)
Calvert Cliffs, MD plus two other sites
EPR (3)
Will go to COL but submit siting information early
First submittal - FY 2008
Detroit Edison
Fermi, MI
Not yet determined
Not yet determined
FY 2008
Dominion
North Anna, VA
ESBWR (1)
Under review, approval expected 2007
FY 2008
Duke
William States Lee, Cherokee County, SC
AP1000 (2)
-
FY 2008
Duke
Davie County, NC
Not yet determined
Under consideration
Not yet determined
Duke
Oconee County, SC
Not yet determined
Under consideration
Not yet determined
Entergy
River Bend, LA
ESBWR (1)
-
FY 2008
Entergy (NuStart )
Grand Gulf, MS
ESBWR (1)
Approved April 2007
FY 2008
Exelon
Clinton, IL
Not yet determined
Approved March 2007
Not yet determined
Exelon
Matagorda and Victoria County, TX
ESBWR (1)
-
FY 2009
Florida Power & Light
Turkey Point, FL
Not yet determined (2)
Not yet determined
FY 2009
NRG Energy / STPNOC
Bay City, TX
ABWR (2)
-
Under Review
PPL Corp.
Susquehanna, PA
Not yet determined
Not yet determined
Not yet determined
Progress Energy
Harris, NC; Levy County, FL
AP1000 (2); AP1000 (2)
-
Harris - FY 2008; Levy County, FL - FY 2008
South Carolina Electric & Gas
Summer, SC
AP1000 (2)
-
FY 2008
Southern Company
Vogtle, GA
AP1000 (2)
Under review, Approval expected early 2009
FY 2008
Texas Utilities
Comanche Peak, TX
APWR (2)
-
FY 2008
TVA (NuStart )
Bellefonte, AL
AP1000 (2)
-
Under Review
FY - Federal Fiscal Year, CY - Calendar Year
Updated: 11/07
----------------------------------------------------------------
Sander C. Perle
President
Global Dosimetry Solutions, Inc.
2652 McGaw Avenue
Irvine, CA 92614
Tel: (949) 296-2306 / (888) 437-1714 Extension 2306
Fax:(949) 296-1144
E-Mail: sperle at dosimetry.com
E-Mail: sandyfl at cox.net
Global Dosimetry Website: <http://www.dosimetry.com/>
http://www.dosimetry.com/
Mirion Technologies Website: http://www.mirion.com/
More information about the RadSafe
mailing list