Interesting perspective. I suppose the theory is that if there aren't a
number of new plants planned to meet their speculated number to be
considered a "renaissance", then this doesn't exist. Compared to the number
of plants evaluated since TMI, the current situation for new NPPs is more
then a renaissance! The following is a list of just the plants being
considered in the USA posted by the Nuclear Energy Institute (NEI):

 


New Nuclear Plant Status

 

 

 

 

 


 


 

 

 

 

 


Company

Site(s)

Design, # of Units

Early Site Permit (ESP)

Construction / Operating License Submittal


Alternate Energy Holdings

Bruneau, ID

EPR

-

FY 2009


Amarillo Power

Vicinity of Amarillo, TX

EPR

-

FY 2009


AmerenUE

Callaway, MO

EPR

-

FY 2008


Constellation (UniStar)

Calvert Cliffs, MD plus two other sites

 EPR (3) 

Will go to COL but submit siting information early

First submittal - FY 2008


Detroit Edison

Fermi, MI

Not yet determined

Not yet determined

FY 2008


Dominion

North Anna, VA

 ESBWR (1) 

Under review, approval expected 2007

FY 2008


Duke

William States Lee, Cherokee County, SC

 AP1000 (2) 

-

FY 2008


Duke

Davie County, NC

 Not yet determined 

Under consideration

Not yet determined


Duke

Oconee County, SC

 Not yet determined 

Under consideration

Not yet determined


Entergy

River Bend, LA

ESBWR (1)

-

FY 2008


Entergy (NuStart )

Grand Gulf, MS

ESBWR (1)

Approved April 2007

FY 2008


Exelon

Clinton, IL

 Not yet determined 

Approved March 2007

Not yet determined


Exelon

Matagorda and Victoria County, TX

 ESBWR (1) 

-

FY 2009


Florida Power & Light

Turkey Point, FL

 Not yet determined (2) 

 Not yet determined 

FY 2009


NRG Energy / STPNOC

Bay City, TX

 ABWR (2) 

-

Under Review


PPL Corp.

Susquehanna, PA

 Not yet determined 

 Not yet determined 

 Not yet determined 


Progress Energy

Harris, NC; Levy County, FL

 AP1000 (2); AP1000 (2) 

-

Harris - FY 2008; Levy County, FL - FY 2008


South Carolina Electric & Gas

Summer, SC

 AP1000 (2) 

-

FY 2008


Southern Company

Vogtle, GA

 AP1000 (2) 

Under review, Approval expected early 2009

FY 2008


Texas Utilities

Comanche Peak, TX

APWR (2)

-

FY 2008


TVA (NuStart )

Bellefonte, AL

AP1000 (2)

-

Under Review


 

 

 

 

 


FY - Federal Fiscal Year, CY - Calendar Year

 

 

 


Updated: 11/07

 

 

 

 

 

 

----------------------------------------------------------------

Sander C. Perle 
President
Global Dosimetry Solutions, Inc. 
2652 McGaw Avenue
Irvine, CA 92614

 

Tel: (949) 296-2306 / (888) 437-1714 Extension 2306 

Fax:(949) 296-1144

 

E-Mail: sperle at dosimetry.com

E-Mail: sandyfl at cox.net 

 

Global Dosimetry Website:  <http://www.dosimetry.com/>
http://www.dosimetry.com/ 

Mirion Technologies Website: http://www.mirion.com/ 

 

 




More information about the RadSafe mailing list