[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Maine Yankee Pres. Ousted
Below is an article from Reuters. Interesting observations can be
drawn:
1. The Board decided that new leadership was needed after many
problems at the plant. One "positive" point .. they asked for the
resignation of the President, and not a few hundred more good hard
working power plant personnel. Now they should start removing some of
the Board, for haven't they been in power and need to assume some
accountability for the way the company operates.
2. The board wants the next president to be from outside of New
England and ``a bigger organization,'' Yup, that always seems to be
the Utility answer to all problems. Sometimes individuals from
"bigger organizations" bring bigger problems and bigger egos with
them!
3. NRC says the utility has "created and environment where
controlling costs became more important than safety." Really .. what
a surprise, and I suppose this is unique to Maine Yankee .. NOT!
4. The NRC is questioning possible "misrepresentations" regarding
computer codes and power upgrades from the late '80s. If I recall,
the NRC is mandated the overview and licenses the plant. This is very
much like the Millstone fiasco. NRC residents familiar with the plant
came down hard when the fuel offloading process was evaluated, even
though they had been using the same procedures for many years. Seems
that the NRC is once again attempting to delegate away
accountability.
Other observations are evident .. but they can be drawn by each
individual.
PORTLAND, Maine - The president of the troubled
Maine Yankee nuclear power plant was ousted in the first step of a
management reorganization, the plant's directors said Friday.
Maine Yankee President Charles Frizzle agreed to step down
after a series of unscheduled shutdowns at the 24-year-old plant in
Wiscasset, Maine, and criticism from regulators who said management
had created an environment where controlling costs became more
important than safety.
``(The board) decided that Maine Yankee needs new leadership
to deal with deep-rooted cultural issues, a changing regulatory
environment and unprecedented financial pressures,'' said David
Flanagan, president of Maine Yankee's board of directors.
Flanagan, chief executive officer of Central Maine Power
Co., said that a broad restructing of Maine Yankee's management
was being considered and that additional changes were likely in
early 1997.
Maine Yankee is 38 percent owned by Central Maine Power
Co.,with New England Electric System and Northeast Utilities
each owning 20 percent, 7 percent held by Bangor Hydro-Electric
Co., 5 percent by Maine Public Service Co. and 10 percent by
other New England utilities.
Flanagan said the utilities would spend an additional $30
million on maintainence in 1997 and $7 million on capital
projects after an inspection by federal regulators found a
variety of equipment problems.
Among the ideas being considered was a proposal that
management of all independently operated nuclear plants in New
England be consolidated under a single corporation, Flanagan
said.
The 910-megawatt Maine Yankee plant has been forced to go
off-line repeatedly for the past two years because of equipment
problems ranging from cracked steam tubes to missing wires in
key reactor safety systems.
The plant's latest outage began Dec. 6 when engineers
discovered several control room electical cables were improperly
installed. The plant may not return to operation until early February,
spokeswoman Maureen Brown said Friday.
The inspection was requested by Gov. Angus King after an
investigation by the Nuclear Regulatory Commission raised
questions about whether Maine Yankee's emergency core cooling
system was properly licensed during a power upgrade in the late
1980s.
The Justice Department is also investigating allegations
that Maine Yankee misled the NRC about a computor code used to
test the systen. The plant has denied wrongdoing.
The plant has been restricted to 90 percent capacity while a
new computor test was being reveiwed. Gov. King has said he
thinks it is unlikely the plant will be allowed to return to 100
percent capacity.
Frizzle, who has held his post since 1989, will remain with
the company until a successor is selected in early 1997. The
board wants the next president to be from outside of New England and
``a bigger organization,'' Flanagan told reporters.
Sandy Perle
Director, Technical Operations
ICN Dosimetry Division
Office: (800) 548-5100 Ext. 2306
Fax: (714) 668-3149
E-Mail: sandyfl@ix.netcom.com
Personal Homepages:
http://www.netcom.com/~sandyfl/home.html
http://www.geocities.com/CapeCanaveral/1205