[ RadSafe ] query - Fort St. Vrain
Bernard L. Cohen
blc+ at pitt.edu
Mon Dec 17 13:07:32 CST 2007
Many thanks for all the info. I had not realized that it had operated so
long and produced so much electricity.
Sandy Perle wrote:
>
> Everything you ever wanted to know about Fort St. Vrain:
>
>
>
> Built in the shadow of the majestic Rocky Mountains, Fort St. Vrain
> (FSV) was Colorado's only Nuclear Power Plant and America's only
> commercial High Temperature Gas Cooled reactor design. Plans to
> construct FSV were announced in 1965. Work began at the site in
> 1968. Initial hot flow testing of the reactor began in 1972, and
> several years of design problem work followed. The first commercial
> electric power using the reactor was generated from the plant in
> December 1976. Nuclear operations came to a close in 1989 due to
> continuing problems with the plant. Decommissioning of the reactor,
> as well as shipping of all nuclear fuel off-site to a U.S. Department
> of Energy managed facility, was complete in 1992. Fort St. Vrain was
> the first commercial nuclear generating plant in the United States to
> be decommissioned. In 1996, generation from FSV began again, this
> time with a combustion turbine burning natural gas and generating 130
> megawatts of power. A heat recovery steam generator (HRSG) was added,
> and steam was provided to the old main steam turbine. A second gas
> turbine with HRSG was added in 1998, making FSV capable of 500
> megawatts. In May 2001, a third combustion turbine with HRSG was
> added, making the final rated output of the plant 720 megawatts.
>
>
>
> *The Rest of the Story*
>
>
>
> Public Service Company of Colorado (PSC) was researching alternative
> power generation as early as the late 1950s. Plans to build Fort St.
> Vrain were announced on March 13, 1965 and the application to
> construct FSV was filed with the Atomic Energy Commission
> <http://www.nrc.gov/> on October 20, 1966. It would be the first
> commercial scal high temperature gas cooled reactor plant in the
> United States. The plant was to be named after the historic frontier
> fort <http://stvrainsfort.homestead.com> of the same name, once
> located about a mile north of the power plant site.
>
>
>
> Preliminary construction work on FSV began in April 1968 after
> receiving approval from the Colorado Public Utilities Commission
> <http://www.dora.state.co.us/puc/>. The U.S. Atomic Energy Commission
> issued it's construction permit on Sept. 18, 1968 and concrete work on
> the reactor building began. Gulf General Atomic <http://www.gat.com/>
> (GA) was the prime contractor. Sargent & Lundy
> <http://www.slchicago.com/home/> subcontracted to GA for architectural
> and engineering and Ebasco was the principal constructor.
>
>
>
> To meet the earthquake design criteria the reactor building was
> engineered to rest on bedrock. This proved to be a problem right away
> because bedrock was 50 feet down through sandy soil and a water table
> at 20 feet. This major obstacle was overcome by freezing the ground
> around the area to be excavated. A total of 360 fifty-five foot long
> U-tube assemblies, all connected together, were installed in the
> ground in an oval shape around what would become the reactor
> building. A freezing brine solution was pumped through these pipes.
> Three huge refrigeration systems maintained the brine at minus 11
> degrees Fahrenheit. The "freeze wall," as it was known, was started
> on May 6th, and by June 3, 1968, the majority of the wall was frozen.
> The foundation was actually dug down 25 feet below the normal surface
> of the bedrock. Once they reached the shale bedrock during
> excavation, it was found that it deteriorated rapidly upon exposure to
> air. Final excavation and concrete pours were carefully coordinated
> to minimize the deterioration.
>
>
>
> Also in June 1968 construction of the reactor bottom head assembly was
> begun west of the reactor building while the building foundation and
> support ring for the pre-stressed concrete reactor vessel (PCRV) were
> being constructed. This assembly consisted of the steel liner,
> penetrations, and core support floor columns and weighed in at 400
> tons. In February 1969 it was moved on rails to temporary supports
> within the support ring. The support ring was completed on Feb 13,
> 1969. It is a cylinder, 50 feet in diameter with highly reinforced
> walls 3-1/2 foot thick and 33 feet high. It required 575 cubic yards
> of concrete and was completed in one 18 hour continuous pour.
>
>
>
> A different approach was used in the construction of the turbine
> building foundation. Sixty-six caissons were drilled into the bedrock
> and casing were installed. Once the casings were in place they were
> pumped dry and the bedrock was drilled out an additional 6 feet. The
> done, reinforcing steel was lowered into the casing and then the
> concrete was poured.
>
>
>
> Turbine building structural steel was 70% complete by Oct. 1, 1969.
> Turbine generator erection was started at this time.
>
>
>
> Hot Flow testing was begun in June 1972. The pelton wheels
> disintegrated due to cavitation. A pelton cavity nitrogen
> pressurization system was designed and implemented by May 1973.
>
>
>
> Fuel loading to the reactor began on December 27, 1973, after the
> operating license was issued. Fuel loading was completed on January
> 16, 1974, and initial criticality was reached on January 31, 1974.
> The rest of the year and into the early spring of '75 was spent
> working on problems with the contol rod drives, moisture ingress into
> the reactor, and pelton wheel cracks.
>
>
>
> Rise-To-Power testing to 2% occured in April 1975. However, as a
> result of the Browns Ferry fire
> <http://www.ccnr.org/browns_ferry.html>, an internal PSC cable
> segregation audit was conducted. In June, the Nuclear Regulatory
> Commission <http://www.nrc.gov/> (NRC) ordered a full audit of all
> essential and associated non-essential cables with respect to
> compliance with the Final Safety Analysis Report. The reactor
> remained shut down during all these audits. Another problem, internal
> leakage in 15 of the control rod drive assemblies, required the rest
> of '75 and early '76 to resolve.
>
>
>
> On July 6, 1976, FSV reached power levels greater than 2%. However,
> the "C" helium circulator had to be replaced due to excessive purified
> helium leakage from the penetration interspace into the pre-stressed
> concrete reactor vessel (PCRV). October to November saw rise-to-power
> testing and minor modifications to the startup bypass pressure control
> system and steam/water dump relay system.
>
>
>
> *_First Power Generation_*
>
>
>
> On December 11, 1976, FSV generated its first electrical power to the
> grid using reactor power.
>
>
>
> Core thermal fluctuations were observed on November 23, 1977. Reactor
> power was reduced to 68% power. Then a small steam generator tube
> leak was detected on November 30th, and the reactor was manually shut
> down so repairs could be made.
>
>
>
> The turbine was again placed on line on April 3, 1978, and testing was
> begun to determine the nature of the thermal fluctuations observed
> earlier. The NRC had imposed a 70% reactor power limit (which was
> below the threshold of the thermal fluctuations).
>
>
>
> The reactor was shut down for first refueling on February 8, 1979.
> Refueling was completed on May 2nd and the reactor was taken critical
> on May 26th. In June, PSC signed an agreement to assume ownership of
> the plant from General Atomics (GA). The reactor was operated at less
> than 2% power for testing until July, when the turbine was once again
> put on line to generate electrical power. Commercial operation of the
> plant officially began on August 1, 1979.
>
>
>
> In October, the reactor was shut down for the installation of region
> constraint devices, better known as "Lucy Locks." The lucy locks
> were installed to address the core fluctuations. Research by GA and
> PSC engineering had come to the conclusion that the blocks were
> shifting around slightly under power. They reasoned that the Lucy
> locks would hold the the block columns together and prevent the
> fluctuations. Lucy locks in place, the reactor was taken critical on
> December 25th. Our fluctuation problems were cured. However a
> problem was found on the "B" helium circulator primary seal, and the
> reactor was soon shut down again.
>
>
>
> The "B" helium circulator was replaced (a huge job), and the turbine
> was back on line on March 16, 1980. In August, the plant was shut
> down for required surveillances (testing) and planned maintenance but
> was back on line, generating power on October 8th.
>
>
>
> Excessive interspace leakage on the Loop 2 steam generator
> penetrations required a shutdown on March 22, 1981, but FSV was back
> on line with the generator on April 13. However, turbine high
> vibration caused a turbine trip, resulting in a reactor scram on May
> 13th.
>
>
>
> Rather than start back up, the second refueling outage was begun a
> little ahead of schedule. Refueling was completed, the reactor taken
> critical, and the generator was back on line on July 26, 1981. On
> November 6th, the reactor reached 100% power. This was great day!
> However, the reactor was shut down on November 9th to begin the "loop
> split" outage in order to create two independent paths for buffer
> helium for better reliability.
>
>
>
> The loop split modifications were completed and the reactor taken
> critical on February 11, 1982. On Feb. 22nd, the reactor was manually
> scrammed due to high moisture, and two control rods failed to properly
> insert. Three additional rods exhibited a tendency to stick in the
> full-out position. A program was initiated to exercise the control
> rods and all were operating properly by February 23rd. The reactor
> was taken critical on April 2nd and the generator put on line on April
> 4 but the plant was shut down again on April 20th to repair a core
> supposrt floor tube leak and test the reserve shutdown system. On May
> 3rd the reactor was taken critical again and the generator was placed
> on line on May 7th. FSV scrammed again on September 30th. In October
> the NRC granted release from the 70% power limitation imposed during
> the thermal fluctuations. The reactor was taken critical for training
> during the first week of November but high primary coolant moisture
> problems kept FSV at low power or shutdown.
>
>
>
> The turbine generator was placed on line on January 1, 1983 but high
> primary coolant moisture scrammed the reactor again on January 28th.
> The generator was back on line again on February 8th but the reactor
> was manually scrammed on February 14th after the loss of the "B"
> instrument power inverter. The reactor was kept shut down while a
> possible core support floor leak was investigated. The generator was
> back on line on March 9th and scrammed again on high moisture on March
> 17th. The reactor was brought on line again on May 24th, but power
> was limited due to high moisture. The moisture gradually decreased,
> and the generator was finally placed on line on July 16th. Things ran
> pretty well for a while.
>
>
>
> Next, FSV experienced high vibration problems with "C" boiler feed
> pump. Reactor power was taken to 80%. Vibration problems continued
> with the boiler feed pump. Consultants were called in and various
> avenues were tried to solve the problem to no avail. By October
> reactor power was up to 85%. However, on November 9th, the boiler
> feed pump seized up and tripped. If that wasn't enough, on December
> 8th the reserve auxiliary transformer deluge system was activated by
> high winds resulting in a turbine trip and reactor scram. The reactor
> was immediately taken critical and the steamer was back in service on
> December 11th.
>
>
>
> On January 20, 1984, the reactor was shut down for refueling, a
> turbine overhaul and electrical modifications. In February the
> Colorado State Public Untility Commission recommended a $526,000.00
> rebate to the Public Service customers, due to the poor performance of
> the plant.
>
>
>
> In March an inspection of the PCRV tendons revealed failed strands in
> the tendon bundles.
>
>
>
> In April, while FSV was awaiting release to go to power from 2%,
> problems arose with sticking orifices in regions 12 and 30. The
> region 12 control rod drive assembly had to be replaced, but region 30
> freed up after excercise. Permission to go above 2% power was
> received from the NRC on May 16th, after their evaluation of the PCRV
> tendon wire degradation. The process of drying out and gradual
> reactor power increase continued until June 12 when the generator was
> placed on line. However, due to moisture, reactor power could only
> slowly be increased. Then on June 22nd a sudden pressure relay on the
> 4160/480V transformer #1 caused a trip of the 480VAC essential bus 1A
> and subsequently tripped the "A" helium circulator, due to a bearing
> water upset. Trying to recover from this incident, we scrammed on
> high reactor pressure on June 23. During this event, six of the
> thirty-seven control rod paris failed to automatically insert. A
> powered insertion to the stuck rods was successful. Cold shutdown
> conditions were achieved by the initial scram, however. This scram
> signaled the beginning of an extensive control rod drive refurbishment
> program.
>
>
>
> During a test of the reserve shutdown system in Novemeber 1984 for
> control rod drive #21, the boron balls failed to discharge properly
> from their hopper. A event report was filed with the NRC. In
> December, helium circulator A was removed and shipped to San Diego for
> repairs on an interspace bearing water leak.
>
>
>
> By February 1985, control rod drive refurbishment was in full swing.
> The helium circulator was returned from San Diego in March. During
> the repair work at San Diego, GA Technologies discovered chloride
> stress corrosion on some of the internal bolting. Therefore, the rest
> of the circulators would have to be removed and inspected. One by
> one, the circulators were removed, repaired and reinstalled. The
> on-going control rod drive work was completed in June 1985, at about
> the same time as the circulator repair work.
>
>
>
> Permission to start up the reactor (at loads up to 15% until
> Environmetal Qualification issues were resolved) was rececived on July
> 19 and the reactor was taken critical the next day. A high moisture
> scram occured on July 23rd, and the reactor remained shutdown for a
> time for primary coolant cleanup. A new digital valve that had been
> installed on on "A" circulator experienced leakage and was replaced
> with the original valve.
>
>
>
> The reactor was taken critical a few times during the summer of 1985
> to try to dry out the primary coolant but the turbine was never placed
> on line. In November the reactor was shutdown for mandated
> Environmental Qualification modifications.
>
>
>
> In January 1986, while returning a clearance on "D" helium circulator,
> a water ingress into the PCRV of approximately 300 gallons occured.
> The reactor was taken critical on February 14th and power was slowly
> increased during March, while primary coolant cleanup continued. On
> April 3, a major snow storm caused voltage upsets on the grid,
> resulting in an automatic shutdown of Loop 2 and the isolation of "B"
> purification train. Management directed a manual scram. The reactor
> was up again on April 6th, and the turbine on line on April 11th. On
> April 27, an automatic reactor scram was generated accidently due to a
> routine surveillance test on the plant protective system (PPS). The
> generator was placed back on line on April 29.
>
>
>
> On May 6th, an electrical grid transient occured which increased
> reactor power to a maximum of 39.2% (FSV was limited to 35% power at
> the time by the NRC). Leakage through a main steam bypass pressure
> control valve upset the overall plant, but the problem was corrected
> and operation returned to normal. Steps were taken to prevent reactor
> power from increasing above 30%.
>
>
>
> *_"EQ"_*
>
>
>
> On May 30th the turbine was taken off line, and on May 31st the
> reactor shut down for government mandated Environmental Qualification
> (EQ) modifications. In June, clearances were hung on the circulating
> water system, resulting in flooding the pump pit. All affected motors
> were removed for inspection and repair. During the EQ outage, staff
> at the plant swelled to an all time high of 965. This number included
> contractor and PSCo personnel.
>
>
>
> Next, on July 7, 1986, the NRC imposed civil penalties on Fort St.
> Vrain for the May 6 over power event ($75,000) and for inadequate
> protection of protected and vital areas ($65,000).
>
>
>
> On September 24, 1986, Public Service reached an agreement to settle
> all litigation concerning Fort St. Vrain. The settlement removed FSV
> from the company's rate base, provided customer refunds, and reduced
> electric rates. The plant was to be run essentially as an independant
> power producer and could charge 4.8 cents per kWh.
>
>
>
> In March 1987 FSV completed the Environmental Qualification program,
> and on June 17th the NRC voted to allow FSV to return to power, not to
> exceed 82%. Unfortunately, on July 28th a purified helium leak was
> found in the interspace of "D" circulator. The reactor was shutdown
> again and "D" circulator was removed and sent back to San Diego. A
> spare circulator was installed. The reactor was again taken critical
> on September 30.
>
>
>
> On October 2 a hydraulic oil fire broke out in the area of a hydraulic
> valve (HV-2292) in the turbine building. A manual reactor scram was
> inserted because of an indicated loss of primary and secondary coolant
> flow. The fire was extinguished by the plant fire brigade. Repairs
> were made.
>
>
>
> The reactor was again taken critical on December 11th. By January 16
> 1987, FSV was at 77% reactor power, beginning the first sustained
> period above 72% power since 1983.
>
>
>
> FSV set a new record for total net generation during a single month of
> 160,184 MWhe during March 1988. In April more problems arose again
> and the plant was up and down, due to circulating water problems and
> electrical system upsets. However, in June FSV set another new record
> for generation.
>
>
>
> *_End of Nuclear Operation Announced_*
>
>
>
> However, in December 1988 the decision was made by the board of
> directors of Public Service Company that Fort St. Vrain would be shut
> down for good. The NRC was notified that the plant would shutdown no
> later than June 30, 1990.
>
>
>
> In March 1989 the independent safe fuel storage installation (ISFSI)
> request for proposal was sent out. The preliminary decommissioning
> plan was submitted in June. In July a new generation record for a
> one-month period was attained and Foster Wheeler <http://www.fwc.com/>
> was selected as the ISFSI vendor.
>
>
>
> The plant was returned to power service on April 9 following a reserve
> shutdown problem. FSV reached 80% reactor power on May 29.
>
>
>
> The summer of '89 was a hot one and Public Service set an all time
> record for power output. For once, FSV was up and fully loaded!
>
>
>
> On July 30th the plant recorded an all time monthly record power
> production of 178,221 net megawatt-hours. On August the 4th FSV
> employees celebrated the outstanding recent performance of the plant
> and the new record with a picnic on the front lawn. There was
> volleyball, horseshoes, a dunk tank (proceeds of payment to "dunk your
> favorite boss" went to United Way) and enough food for 500 employees.
>
>
>
> *_The End Came Early!_*
>
>
>
> On August 18th during routine surveillance testing a control rod drive
> assembly was found to malfunction. The plant was shut down and
> preparations for repair and return to service were begun. However,
> during a routine walkdown by one of the plant engineers, hairline
> cracks were found in the inconel steel main steam ring header
> immediately below the reactor. This ring header received steam from
> the steam generators in the reactor prior to the steam's short trip to
> the turbine generator. The hairlinge cracks proved to be */the/* last
> straw for Fort St. Vrain. Based on this turn of events, the PSC Board
> of Directors announced the decision to terminate operations at Fort
> St. Vrain effective on August 29, 1989.
>
>
>
> From November 1989 through February 1990, fuel was removed from twelve
> reactor regions and stored in the fuel storage wells located on the
> fuel deck in the plant reactor building.
>
>
>
> The Nuclear Regulatory Commission (NRC) issed the Confirmatory
> Shutdown Order for FSV in May 1990. In June, the Independent Spent
> Fuel Storage Installation (ISFSI) license application, safety analysis
> report, and environmental reports were submitted to the NRC. The
> ISFSI was needed because plans to ship Fort St. Vrain's spent fuel to
> the Department of Energy facilities in Idaho under a 1965 contract
> were halted by a lawsuit filed by the State of Idaho. So, the ISFSI
> was considered as a contingency.
>
>
>
> In July the Westinghouse team was selected as the decommissioning
> contractor.
>
>
>
> The decision to proceed with construction of the ISFSI was made in
> January 1991, and construction began in February. In May, a
> "possession only" license was issued by the NRC. The Final Safety
> Analysis Report was submitted to the NRC in July 1991.
>
>
>
> In October 1991, three shipments (eighteen fuel elements) of spent
> fuel were sent to the Idaho National Engineering Lab
> <http://www.inel.gov/>. Also in October, all non-union employees were
> required to bid on the remaining positions for "early dismantlement".
> This was a very tramatic time that none of us will forget. An
> employee either got picked for a position or got a 90-day notice.
> Simple. On November 22nd the names of 38 non-barganing unit personnel
> were announced. The union employees went through a similar procedure
> based on seniority.
>
>
>
> The NRC issued the Materials License and Safety Analysis Report for
> ISFSI in November 1991 and the first load of spent fuel was deposited
> there on December 27th. Fuel shipping was completed into the ISFSI
> on June 10, 1992 and the nuclear security and nuclear fitness for duty
> programs were terminated shortly thereafter. Fort St. Vrain received
> the Public Service Company Eagle Award as recognition for completing
> defueling "months ahead of schedule--saving the company millions of
> dollars." The */PSCo Times/* noted that the award was "even more
> impressive considering many of those employees were literally working
> themselves out of a job."
>
>
>
> On June 26th more than 700 past and present employees came together to
> celebrate the final defueling of the reactor at Fort St. Vrain. A
> grand time was had by all on the front lawn of the now silent plant.
> At this time, Del Hock, president, chairman and CEO of PSCo, presented
> the 1991 President's Safety Award to the employees of the plant for
> the most hours worked without a lost-time injury.
>
>
>
> *_Decommissioning_*
>
>
>
> Decommissioning of the plant--returning it to a safe and
> non-radioacive site--began immediately after defueling was complete.
> Decommissioning was expected to take 3 years. Also at this time,
> plans to convert the plant to natural gas were being considered.
>
>
>
> In the October 4, 1993 issue, of the */PSCo Times/*, Bob Gunnerson,
> decommissioning project engineer, reported that the last section of
> the 15-foot thick concrete reactor top head (the top of the reactor
> vessel) had been removed. Diamond wire saws were used to cut the
> tophead apart. In all there were 12 pie shaped pieces, each weighing
> around 110 tons, or in total, 17,500 cubic feet of concrete.
>
>
>
> With the tophead removed, work could begin to remove the top of the
> PCRV steel liner and then go on to the 1,500 graphite blocks which
> made up the remainder of the reactor core (after the removal of the
> fuel blocks during defueling). The reactor was flooded with
> constantly filtered water to provide as much shielding from the
> remaining radiation as possible.
>
>
>
> The reactor core support floor, weighing in at 340 tons, was removed
> Feb 8, 1995. With the reactor vessel still flooded, divers actually
> had to swim under the core support floor to cut it lose from the core
> support floor posts with torches. It was then sectioned into two
> pieces and lifted out, using the reactor building overhead crane.
>
>
>
> *_Repowering_*
>
> (FSV rides again!)
>
>
>
> Construction of the first gas turbine, a General Electric Frame 7
> <http://www.gepower.com/dhtml/corporate/en_us/assets/gasturbines_heavy/prod/ms7001fa.jsp/>
> called FSV Unit 2, was nearing completion in March 1996 and the unit
> was test fired a few times. Black & Veatch
> <http://www.bv.com/bv/index.htm> was the primary contractor on this
> unit. On May 6, 1996, the unit came on line for commercial operation
> at the "repowered" Fort St. Vrain. Pubic Service initally billed the
> plant as a "peaking unit capable of 130 megawatts (MW) of power." The
> June 24, 1996 issue of the */PSCo Times/ *quoted station director,
> Marty Block, about the repowering: "Start up of the combustion
> turbine marked an important day for all of the employees here--and
> certainly for all those who worked so hard over the years when this
> was a nuclear facility. . .We're just glad to be back as a power plant."
>
>
>
> Meanwhile, construction of the heat recovery steam generator (HRSG)
> for unit 2 proceeded at a rapid pace. The HRSG would take the hot
> exhaust from the combustion turbine and make steam to power the old
> steam turbine in the main plant building. The HRSG also has
> supplemental natural gas burners to provide additional heat during
> times where peak load is required. On March 21, 1998, unit 2 was
> fired with the damper door open to the HRSG for initial heat up and
> testing. On May 5, 1998, with HRSG testing completed, steam was
> admitted to the original steam turbine and the unit was syncronized to
> the grid for the first time in 9 years. At this point, FSV was
> capable of about 230 MW of power total to the grid.
>
>
>
> Construction of Unit 3, FSV's second gas turbine and HRSG, was
> completed by January 1999 by principal contractor, Utility Engineering
> <http://www.ueplaza.com/>. Unit 3 was started up in simple cycle
> (without the HRSG) on January 12, and syncronized to the grid. On
> April 24, the unit was fired in combined cycle and the steam turbine
> was syncronized to the grid for the first time using unit 3 steam.
> Now FSV was capable of just over 500 megawatts on a cool day. (The
> units outputs are highly effected by the ambient temperature.)
>
>
>
> Construction of FSV Unit 4, the third and final gas turbine and HRSG,
> was begun in the summer of 2000. First fire of unit 4 was early May
> 2001. Utility Engineering was also the primary contractor for this
> unit and The Industrial Company (TIC) <http://www.tic-inc.com/> was
> their principal constructor.
>
>
>
> On October 2nd, Public Service Company of Colorado officially became
> Xcel Energy <http://www.xcelenergy.com/>. Xcel Energy was the result
> of the merger of New Centuries Energies and Northern States Power on
> August 18th. Headquarters for the new company are in Minneapolis. At
> this time, Xcel Energy had 11,800 employees in 12 states and served
> 3.1 million customers.
>
>
>
> In February 2001, Fort St. Vrain exceeded the total output generated
> by the plant during the nuclear days. This was a bittersweet date for
> those who were at FSV in those days.
>
>
>
> On April 25, 2001, unit 4 was put on the turning gear in preparation
> for first fire. Unit 4 has a selective catalytic reduction system
> (SCR) for reducing stack emissions of the oxides of nitrogen (NOx).
> The SCR was manufactured by Mitsubishi Heavy Industries
> <http://www.mhi.co.jp/indexe.html>. First fire was a brief flame on
> the 28th. A sustained flame was attained on the 29th and on the 30th,
> and the unit was run for about 4 hours at full speed and no load. As
> with the first two combustion turbines, these events began the arduous
> task of combustion tuning (for most stable flame and lowest
> emissions), steam blows (to clean out the HRSG and steam lines), and
> stack certification testing (to certify the stack emissions monitoring
> system).
>
>
>
> On May 21, 2001, unit 4 was put into service for the first time,
> purely to produce power for the grid. It ran in simple cycle and full
> load during the combined cycle startup of unit 3 as FSV began putting
> the other units and steam turbine back on line for the summer. On May
> 22nd, unit 4 was put in combined cycle for the first time, supplying
> steam to the steam turbine. On May 24, 2001, unit 4 was pronounced
> "commercial," bringing to a close the $283 million repowering of FSV.
> On May 31st all 3 combustion turbines were running in combined cycle
> mode, supplying steam to the old steam turbine, for the first time.
> The new plant uses 1800 psig and 1000 deg. F. main steam. This is
> believed to be the final configuration of the Fort St. Vrain power
> station. The plant is now rated at 720 megawatts.
>
>
>
>
>
> ----------------------------------------------------------------
>
> Sander C. Perle
>
> President
>
> Global Dosimetry Solutions, Inc.
>
> 2652 McGaw Avenue
>
> Irvine, CA 92614
>
>
>
> Tel: (949) 296-2306 / (888) 437-1714 Extension 2306
>
> Fax:(949) 296-1144
>
>
>
> E-Mail: sperle at dosimetry.com
>
> E-Mail: sandyfl at cox.net
>
>
>
> Global Dosimetry: http://www.dosimetry.com/
>
> Mirion Technologies: http://www.mirion.com/
>
>
>
>
>
--
Bernard L. Cohen
Physics Dept., University of Pittsburgh
Pittsburgh, PA 15260
Tel: (412)624-9245 Fax: (412)624-9163
e-mail: blc at pitt.edu web site: http://www.phyast.pitt.edu/~blc
More information about the RadSafe
mailing list