[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Energy Dept: Laser Cost Doubled
Energy Dept: Laser Cost Doubled
WASHINGTON (AP) - Development of the world's most powerful laser to
monitor the nation's nuclear arsenal without testing - a project
already dogged by cost overruns and delays - could cost nearly three
times its original $1 billion price tag, congressional auditors say.
The Energy Department told the General Accounting Office the cost of
the laser project at Lawrence Livermore National Laboratory in
California has soared to $2.2 billion - twice what it was predicted
to be in 1995. But the GAO, the investigative arm of Congress, said a
more accurate total is closer to $3 billion.
As recently as January, its price was said to be $1.5 billion.
The soon-to-be-released GAO report says that the project has been
mismanaged by Lawrence Livermore and that technical problems as well
as unexpected expenses and scheduling delays were withheld from
outside reviewers and the Energy Department.
While costs have soared, the project has lagged far behind schedule,
with its completion date now put at 2008, six years behind schedule.
The laser, which is to be the most sophisticated and powerful ever
developed, is a key part of the department's nuclear weapons
stewardship program. The project consists of 192 laser beams used to
simulate a nuclear explosion. The beams are to shoot energy onto a
single target, recreating in a laboratory the thermonuclear
conditions caused by a nuclear detonation.
Formally known as the National Ignition Facility, the laser is also
part of a government effort to properly maintain, test and monitor
the nation's nuclear weapons stockpile without resumption of actual
testing of warheads and bombs at the Nevada Test Site.
A draft copy of the GAO report was obtained Wednesday by The
Associated Press from two citizen groups that have been critical of
the National Ignition Facility.
The GAO report attributes the cost overruns to an unrealistic
original budget, poor management at Lawrence Livermore and ``an
absence of effective independent reviews'' and oversight by the
Energy Department.
GAO investigators also found that senior managers of the laser
project withheld their concerns about the technical and management
problems from the Energy Department and the director of the Livermore
Lab, which is operated by the University of California.
Energy Secretary Bill Richardson last year ordered a review of the
laser project after he learned of a $350 million cost overrun.
Since then, the costs have continued to soar, with the Energy
Department sending a $2.2 billion cost estimate to Congress in June,
according to the GAO report.
But the GAO said the actual costs exceed $2.8 billion, and warned,
``technical problems may further drive up'' the cost if they are not
easily resolved.
The cost of related research and development needed for the laser to
be used as planned also have increased, according the GAO, from $1
billion in 1995 to nearly $1.8 billion. The Energy Department
estimates the cost increases to be more modest - no more than $140
million.
Technical problems affecting both costs and the completion schedule
for the laser were first raised in the summer of 1998 and documented
over a three-month period in early 1999, the GAO said. Yet,
Livermore's director, Bruce Tarter, told Congress in March 1999 that
the project was ``on budget and on schedule.''
In early 1999, an independent contractor also reviewed the project's
progress ``and did not report any significant cost, schedule or
technical'' problems, although ``over two dozen senior NIF managers
knew the project faced growing problems that threatened both its
costs and schedules,'' according to the GAO report.
``The GAO report shows a pattern of deception involving top
managers,'' said Marylia Kelley, of Tri-Valley Cares, a citizen group
in Livermore that has opposed the project. ``Officials took a see no
evil, hear no evil, speak no evil approach and turned a blind eye to
problems they knew or suspected.''
Kelley's group and another nuclear weapons watchdog organization,
Alliance for Nuclear Accountability, obtained a draft of the GAO
report, which may be released as early as this week. The report had
been requested by the House Science Committee.
------------------------------------------------------------------------
Sandy Perle Tel:(714) 545-0100 / (800) 548-5100
Director, Technical Extension 2306
ICN Worldwide Dosimetry Division Fax:(714) 668-3149
ICN Biomedicals, Inc. E-Mail: sandyfl@earthlink.net
ICN Plaza, 3300 Hyland Avenue E-Mail: sperle@icnpharm.com
Costa Mesa, CA 92626
Personal Website: http://www.geocities.com/capecanaveral/1205
ICN Worldwide Dosimetry Website: http://www.dosimetry.com
************************************************************************
The RADSAFE Frequently Asked Questions list, archives and subscription
information can be accessed at http://www.ehs.uiuc.edu/~rad/radsafe.html