[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

NRC engineers wanted to shut down davis-bessie-messie







Vina K Colley wrote:



>  (The Plain Dealer, Saturday, July 6, 2002, page 1)  NRC engineers

> wanted to shut Davis-Besse07/06/02John Funk, John Mangels and Stephen

> Koff

> Plain Dealer Reporters

>

> Staff engineers at the Nuclear Regulatory Commission last fall wanted

> their bosses to order the shutdown of the Davis-Besse nuclear power

> station by year's end.

>

> They feared there might be dangerous cracks in nozzles in the

> reactor's lid. They were concerned about the lack of inspection

> information they were getting from the plant, according to NRC

> documents. And they realized FirstEnergy Corp. intended to operate the

> reactor without a new inspection beyond the time the NRC considered

> prudent.

>    But top NRC managers ultimately decided not to issue the order.

>

>

> hey

> reasoned

> it

> was "very unlikely" that cracks would cause the lid to rupture. They

> also judged that even if such an accident happened, the public's risk

> was acceptably low. They went along with Davis-Besse's request to

> operate six weeks beyond the Dec. 31 date the agency set for

> inspecting other nuclear plants.

>

> What neither the NRC nor FirstEnergy, Davis-Besse's operator, knew was

> that the reactor not only already had cracks, but also that acid in

> the reactor's coolant had leaked through them and bored a 5- by 7-inch

> hole all the way through the heavy steel lid.

>

> Only the lid's thin stainless steel liner, bulging into the hole, kept

> the radioactive coolant from spewing into the reactor building in an

> unprecedented accident.

>

> NRC Chairman Richard Meserve revealed the internal debate in a letter

> this week responding to questions about the close call at Davis-Besse.

>

> The questions came from U.S. Reps. Marcy Kaptur of Toledo and Edward

> Markey of Boston.

>

> "Had we been aware of the degradation [rust hole], the agency would

> have taken the appropriate regulatory actions to shut down the reactor

> for the required inspection," Meserve wrote.

>

> The NRC's inspector general is examining how the decision to delay the

> Davis-Besse inspection was reached, and whether it mirrored what the

> inspector general found to be a flawed agency decision in a similar

> case two years ago involving a reactor near New York City.

>

> "When Arthur Andersen gets it wrong, the shareholders pay the price,"

> said Steve Fought, legislative director for Kaptur. "If the NRC gets

> it wrong, everybody could end up paying the price." Fought said

> Kaptur's congressional staff is reviewing Meserve's letter and its

> hundreds of supporting documents. "It's not just a question about the

> company," he said. "It's a question about how the NRC acted too."

>

> To justify a shutdown order, the NRC would have had to prove the

> action was necessary to protect the public, Meserve wrote.

>

> Relying on FirstEnergy's own risk assessment calculations, the NRC

> staff determined that operating the plant past Dec. 31 could increase

> the risk of a reactor core-damaging accident beyond what the agency

> normally would consider acceptable. But the chance of such an accident

> posing a danger to the public was low enough to be within the agency's

> allowable limits.

>

> Based on the information the agency had at the time, NRC managers

> decided they didn't have enough reason to halt Davis-Besse's operation

> early.

>

> "After considerable deliberation and increased [FirstEnergy]

> management attention, it is the staff's judgment that sufficient

> information is available to justify operation of the Davis-Besse

> facility until Feb. 16," according to a confidential NRC staff report

> issued Nov. 30, 2001. The date was a compromise, since FirstEnergy

> originally had sought to operate until March 31.

>

> During the shutdown, workers inspecting for cracks in the nozzles that

> allow control rods to pass through the reactor lid accidentally found

> the rust hole, covered by a thick layer of "lava-like" boric acid. The

> company is estimating it will spend $200 million buying replacement

> power and repairing the crippled reactor.

>

> The issue that prompted the debate within the NRC about what to do

> with Davis-Besse began last year. In early 2001, operators of a

> nuclear plant in South Carolina similar to Davis-Besse reported

> finding cracks in some of the stainless-steel tubes, or nozzles, that

> allow the reactor's control rods to pass through the lid and into the

> nuclear core.

>

> The cracks were large and threatened to encircle the nozzles,

> increasing the risk they would fracture and shoot out of the lid,

> propelled by the reactor's high operating pressure.

>

> The NRC last August alerted utilities across the nation operating all

> 69 pressurized water reactors like Davis-Besse. They asked 13 plants,

> including Davis-Besse, that were at the greatest risk for having the

> kinds of cracks found at the South Carolina facility to explain why

> they believed their reactors could safely operate beyond Dec. 31.

>

> FirstEnergy said it had reviewed inspection records from 1998 and 2000

> and had concluded that there was no sign of leakage from nozzle

> cracking. It made this argument even though its own records showed

> that much of the reactor lid was caked with brown/red deposits of

> boric acid more than an inch thick and that workers had to use

> crowbars to remove the rock-hard deposits.

>

> The company wanted to delay inspection until its long-scheduled April

> 1, 2002, shutdown for refueling. That way, costs would be lower and

> inspectors' exposure to radiation would be limited.

>

> When the skeptical NRC staff asked for more information, FirstEnergy

> promised that it would lower the temperature of the reactor to limit

> growth of any cracks. It also pledged to defer inspection and

> maintenance of safety systems to keep them available in case of an

> accident.

>

> Finally, the company told the NRC it would give reactor operators

> special training on how to handle the kind of lid rupture the agency

> believed could happen at Davis-Besse.

>

> In an August internal memo, an NRC analyst worried that the operators'

> current level of training might be inadequate.

>

> "There is concern that the event would evolve in a different manner

> than that expected by plant operators and cause confusion," a staffer

> in the Division of Systems Safety and Analysis wrote.

>

> Union of Concerned Scientists nuclear engineer David Lochbaum said

> using risk assessment analysis to justify a six-week extension is

> flawed, charging that the NRC was merely looking for an excuse to

> allow the company to continue operating.

>

> "If you think nozzles are broken and you are not allowed to operate

> with broken nozzles, then I think your answer is that that is your

> answer," Lochbaum said.

>

> "When you don't like that answer . . . you play with the numbers

> again. That's what they did."© 2002 The Plain Dealer. Used with

> permission.

>



--

Coalition for Peace and Justice and the UNPLUG Salem Campaign; 321 Barr

Ave., Linwood, NJ 08221; 609-601-8583 or 609-601-8537;

ncohen12@comcast.net  UNPLUG SALEM WEBSITE:

http://www.unplugsalem.org/  COALITION FOR PEACE AND JUSTICE WEBSITE:

http://www.coalitionforpeaceandjustice.org   The Coalition for Peace and

Justice is a chapter of Peace Action.

"First they ignore you; Then they laugh at you; Then they fight you;

Then you win. (Gandhi) "Why walk when you can fly?"  (Mary Chapin

Carpenter)





************************************************************************

You are currently subscribed to the Radsafe mailing list. To unsubscribe,

send an e-mail to Majordomo@list.vanderbilt.edu  Put the text "unsubscribe

radsafe" (no quote marks) in the body of the e-mail, with no subject line.

You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/