[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
U.S. Congress approves Yucca nuclear waste dump
Index:
U.S. Congress approves Yucca nuclear waste dump
Nevada vows to fight on against Yucca nuclear dump
Many a Molehill Before Nuke Waste Finds Mountain
Radioactive mineral moved from education ministry to Aichi
=================================
U.S. Congress approves Yucca nuclear waste dump
WASHINGTON, July 9 (Reuters) - The U.S. Senate gave final
congressional approval on Tuesday to President George W. Bush's
decision to bury deadly nuclear waste from across the nation in
Nevada's Yucca Mountain, setting aside state safety concerns already
being argued in federal court challenges.
Senators approved a resolution to override Nevada's veto of the
administration's plan to put the country's first permanent nuclear
waste repository in the Nevada desert, 90 miles (150 km) northwest of
Las Vegas. The U.S. House of Representatives approved it in May.
The Senate vote effectively clears the way for the U.S. Energy
Department to apply to the Nuclear Regulatory Commission to license
the $58 billion project. The facility is scheduled to open in 2010
and hold 77,000 tons (70,000 metric tonnes) of radioactive material
that the Environmental Protection Agency says must be isolated for
10,000 years.
The resolution passed the Senate on a voice vote after clearing a
procedural hurdle, 60-39.
Fifteen Democrats joined 45 Republicans in approving a pivotal motion
to consider the resolution. Three Republicans and one independent
joined 35 Democrats in opposing it.
There are about 100 nuclear power plants across the country. Spent
fuel from these plants is highly radioactive and is stored at 131
sites in 39 states. Many storage tanks are nearly full and the
government has faced lawsuits for failing to meet a 1998 deadline to
open a permanent storage site.
"Now more than ever, we need Yucca Mountain," declared Sen. Frank
Murkowski, an Alaskan Republican.
NOT IN MY STATE
Nevada filed federal lawsuits to try to stop the project before and
after Bush accepted a recommendation by U.S. Energy Secretary Spencer
Abraham in February to build the facility in the state.
Abraham says $4 billion in studies over the past 20 years have found
Yucca Mountain to be a safe site.
"We need to move ahead," he said after Tuesday's vote. "We need
nuclear energy to supply America with energy security -- 20 percent
of our electricity is generated by nuclear power."
Nevada Gov. Kenny Guinn declared in a statement on Tuesday, "Now the
process moves to the federal courts where the playing field is level
and Nevada's factual, scientific arguments will be heard by impartial
judges. .... We are highly confident."
Guinn in April vetoed Bush's decision to put the nuclear dump in his
state. Under the 1982 nuclear law, a governor may veto a president's
decision to put a nuclear waste repository in his or her state. But
the veto can be overridden by Congress with a majority vote in each
chamber.
Opponents, including a number of environmental groups, argue Yucca
Mountain and shipments of nuclear waste to it would provide an
inviting target for terrorists.
But backers, who include many of the nation's top businesses, contend
it would be safer to have the waste in one site rather than scattered
at facilities nationwide.
Some senators who voted for the project admitted they did so because
they feared that if it was killed, nuclear waste would be sent or
left in their states.
As Sen. Robert Bennett, a Utah Republican, put it: "Given the choice.
... I would rather have the waste go through Utah than to Utah."
NOT DEFEATED YET
Senate Democratic Whip Harry Reid of Nevada, who has helped lead the
charge against the project, refused to concede defeat.
"If they think this is the end they are sadly mistaken," said Reid,
noting he could still oppose funding and planned to assist in his
state's lawsuits.
Leading proponents argued Congress needed to approve Yucca Mountain
or begin all over again with what has been more than a two-decade-old
process to find a site.
Such a delay would be a big blow to the nuclear industry, which has
long sought a permanent disposal facility, as well as the federal
government, which has promised to deliver one.
"If not now, when in the world are we going to do it? ... And if not
in this place, where?" Senate Minority Leader Trent Lott, a
Mississippi Republican, asked in urging approval.
---------------
Nevada vows to fight on against Yucca nuclear dump
By Cathy Scott
LAS VEGAS, July 9 (Reuters) - Nevada officials vowed on Tuesday to
fight on against government plans to bury nuclear waste at Yucca
Mountain, saying the program will dump thousands of tonnes of deadly,
radioactive material within a dice's throw of the state's glittering
casinos and fast-growing suburbs.
The Bush administration plan received final congressional approval on
Tuesday, opening the way for the Nuclear Regulatory Commission to
license the $58 billion Yucca Mountain project.
It is scheduled to open in 2010 and hold 77,000 tons (70,000 metric
tonnes) of radioactive material that the Environmental Protection
Agency says must be isolated for 10,000 years.
But Nevada officials said they would continue the court fight against
the project -- which could mean more delays for a nuclear waste
proposal which is backed by both President George W. Bush and the
nuclear industry.
"The U.S. Senate vote today is the beginning of Nevada's legal and
regulatory fight to stop the Yucca Mountain project," said Nevada
Gov. Kenny Guinn, who vetoed the original proposal, in a statement.
"Now, the process moves to the federal courts, where the playing
field is level and Nevada's factual and scientific arguments will be
heard by impartial judges."
Nevada has already filed suits in federal court to try to stop the
dump from being built at Yucca Mountain, and will now argue to the
NRC that the mountain is an unsafe site for nuclear waste, despite
administration claims to the contrary.
In Las Vegas, just 95 miles (150 km) from the proposed facility,
officials said the federal government was ignoring the safety
concerns of the region's 1.4 million people.
"The fight won't be over today, even if there is a vote in favor of
it," said Elaine Sanchez, a spokeswoman for Las Vegas Mayor Oscar
Goodman, who was in Washington Tuesday for last-ditch lobbying
against the project.
"We will have our day in court," Sanchez said. "It's only a matter of
time before there's an accident transporting nuclear waste. It'll be
a moving target for terrorists. The world has changed and these
things need to be considered."
Opinion polls have shown that most Nevadans are not willing to gamble
on nuclear safety so close to home.
A poll earlier this year conducted by Mason-Dixon Polling & Research
Inc. of Washington, D.C. for the Las Vegas Review-Journal, shows that
83 percent of Nevadans oppose the Yucca Mountain site, although 68
percent said they believed it was inevitable that the program would
be approved.
One Nevadan who did not oppose the project was former Nevada Gov. Bob
List, who represents the Nuclear Energy Institute.
List said that Nevada would have to learn to live with the prospect
of a huge nuclear dump in its backyard. "We really need to start
accepting the reality of the situation and figure out ways to turn
this to Nevada's economic advantage -- and there will be economic
advantages for Las Vegas," he told KLAS television over the weekend.
TRUCKS, TRAINS AND NUCLEAR WASTE
The U.S. Department of Energy's plan is to entomb 77 thousand tonnes
of nuclear waste beneath the volcanic ridge northwest of Las Vegas,
where it will remain for 10,000 years.
The highly radioactive material will be shipped from the nation's
nuclear power plants, by rail or truck, to Yucca Mountain. The
proposed routes cross 43 states and potentially pass some 109 cities
with populations of at least 100,000 people.
Las Vegas Mayor Goodman, who has vocally opposed the Yucca Mountain
dump, said transportation was a major concern following the Sept. 11
attacks. "Even the Nuclear Regulatory Commission believes a terrorist
attack on America's nuclear power plants are a real threat," he said
on Tuesday.
Jack Fetters, a conductor for Union Pacific Railroad and a
representative of the United Transportation Union, told Reuters that
conductors and engineers are nervous about moving the waste by rail.
"Workers aren't looking forward to it," Fetters said. "As far as
science goes, I know nothing about that. What I do know is you've got
conductor and engineer fatigue, and maintenance of the cars and rails
issues. I mean, you don't just put it on a train and start sending it
from Maine to Nevada."
On Sunday, about 60 people protested peacefully against the dump in
front of a county building in downtown Las Vegas.
------------------
Many a Molehill Before Nuke Waste Finds Mountain
WASHINGTON, July 9 (NY Times) -- The political support for burying
nuclear waste beneath Yucca Mountain in Nevada may be as strong now
as in 1987, when Congress first picked the site. But the Senate's
approval of the site today, while it lets the Energy Department
proceed, is far from the last word.
What comes next is more complicated than winning the blessing of
Congress: transforming political momentum into sound science and
engineering, and actually creating a functioning repository. That is
likely to take years — if indeed it ever comes to pass.
The Energy Department, Yucca Mountain's prime sponsor, is an old hand
at managing giant, first-of-a-kind projects, but many of them have
horrible histories. The Superconducting Supercollider, an $11 billion
project, was canceled in 1993 after $2 billion had been spent,
falling victim to rising costs and daunting technical problems. The
Clinch River Breeder Reactor, begun in 1970 as a $700 million
project, was canceled in 1974 after $1.5 billion had been spent, as
opponents questioned whether it was worth the effort. For similar
reasons, the modernization of a nuclear fuel plant in Portsmouth,
Ohio, begun in 1977, was canceled in 1985 after $3.5 billion had been
spent. Then there was the nuclear-powered airplane, begun in 1954 and
canceled in 1961 after $1 billion had been spent. By then, there were
overwhelming doubts that it would fly.
Yucca Mountain will be even tougher to pull off, in one regard.
Congress has required that the Energy Department, a mostly self-
regulating bureaucracy, win a license from a sister agency, the
Nuclear Regulatory Commission. That is far from easy, even for
nuclear power companies with long experience getting approval from
the commission for simpler projects. In the 1980's, for example, two
commercial reactor projects in the Midwest, Zimmer and Marble Hill,
were canceled because of licensing difficulties.
"Yucca's not a sure thing," said C. William Reamer, the deputy
director of the commission's waste management division. The Energy
Department will have to lay out "not just their argument, but what
supports their argument" about why the repository will contain the
wastes successfully for 10,000 years, he said.
Thus far, the department does not even have a design. It plans to put
waste in an area unusually subject to rust but has little data on how
its metal canisters will perform. It has a huge environmental impact
statement, but critics say that in its current form, the statement
makes many unverifiable claims.
Because Yucca Mountain is complex, Congress created a committee of
outside experts, the Nuclear Waste Technical Review
Board, to help assess the Energy Department's work. Its chairman,
Jared L. Cohon, who is the president of Carnegie Mellon
University, said today that for all the work the department had done
so far, there was still "a relatively high level of uncertainty"
about
how well it would isolate the waste. Congress may have voted, Dr.
Cohon said, but "that issue is still there."
Too, the Energy Department needs to keep working to understand how
water, which will spread the waste, moves through the
mountain; then it needs to explain this to the public, Dr. Cohon
said.
But right now, the department will probably turn its attention to
preparing a license application. Under the law, the department is
supposed to apply for a license within 60 days of Congressional
approval. But it has told the commission that it will file more than
two years late, by December 2004. In most Energy Department projects,
including this one so far, nothing happens ahead of
schedule and most things happen later.
The nuclear commission is supposed to decide in three years whether
to grant a license, but it may take a fourth. If the staff asks
the department too many questions, the review could easily take
longer, experts say. The commission expects an adversarial
hearing with 8 to 10 parties, each of which can raise questions and
make arguments. In the 1960's and 70's, when the commission
was still licensing power reactors, a hearing with only three or four
parties could drag on for years.
There is more potential for delay in the commission's insistence on a
detailed safety analysis before it grants a license. The Energy
Department's practice is to build major factories while
simultaneously working on critical technical details, a technique
pioneered in
World War II to build the atom bomb, and still in use. For example,
in the 1980's the department started work on a processing plant
in Aiken, S.C., for solidifying liquid wastes, without figuring out
how it would get wastes out of storage tanks and into the plant
without producing flammable gases. Now the solidification plant is
running but is limited in how much waste it can process because
the flammable gas problem has not been solved.
The Yucca Mountain project has something going for it that previous
doomed projects lacked. The federal government needs it to
resolve its commercial dispute with the nuclear utilities. Under the
1982 Nuclear Waste Policy Act, the utilities all signed contracts
with the government, agreeing to pay one-tenth of a cent per kilowatt-
hour generated at their reactors, in exchange for the
government's taking their wastes, beginning in 1998.
But Yucca Mountain also has first-of-a-kind disadvantages. For one,
the Nuclear Regulatory Commission is supposed to decide on
granting a license by applying rules written by the Environmental
Protection Agency. But those rules are being challenged by
Nevada and by the Natural Resources Defense Council, an environmental
group, which argue that the agency gerrymandered the
site's boundaries to allow for excessive leakage. The boundaries look
like a gigantic number 9, with a three-mile ring around the
repository and a tail of about 10 miles in the direction that water
flows underground. Geoffrey H. Pettus, a lawyer with the Natural
Resources Defense Council, called it "an underground septic field."
Nevada has other legal challenges under way, too.
Then there is the fact that Yucca Mountain is too small. The
resolution passed today limits it to 77,000 tons, but the nation will
produce more than 100,000. Congress may have to act again.
-------------------
Radioactive mineral moved from education ministry to Aichi
TOKYO, July 8 (Kyodo) - A company owning about 13 tons of low-level
radioactive monazite that was kept at an education ministry
facility in Tokyo for the past year has moved it to another firm in
Aichi Prefecture, the ministry said Monday.
Nampo Shigen moved the mineral from the Education, Culture, Sports,
Science and Technology Ministry in central Tokyo on June 2
and Sunday to Yamaguchi Taika, a fireproof brick maker located in
Seto in the central Japan prefecture, according to the ministry.
Yamaguchi Taika has already sold 5.4 tons of the monazite to a health
appliance maker and has stored the rest in its Seto factory,
the ministry said.
The ministry did not notify the Aichi prefectural government or the
Seto city government about the transfer of the radioactive
substance in advance, but there will be no problem because the safety
of the storage area has been confirmed, a ministry official
said.
The monazite was mined in Thailand. Nampo Shigen, a trading house
based in Asaka, Saitama Prefecture, wanted to sell it for use
in hot springs or for research purposes.
But demand was poor and the firm had stored it at sites in Saitama,
Chiba, Nagano and Mie prefectures.
It was found to have done this without government permission, and the
storage conditions were below standard. The firm then
transported the monazite to a warehouse in Katsuura, Chiba
Prefecture, but had to abandon that plan because the local government
opposed it.
The ministry had to accept it temporarily, and had kept it in an
underground garage since July last year until the trader could find
an appropriate place for it.
The monazite was kept in metal containers shielded by lead blocks and
sandbags in the ministry garage for safety since extended exposure
could be harmful to humans.
Nampo Shigen has paid 1.3 million yen of 2.38 million yen the
ministry charged it for the storage, according to the ministry.
-------------------------------------------------
Sandy Perle
Director, Technical
ICN Worldwide Dosimetry Service
ICN Plaza, 3300 Hyland Avenue
Costa Mesa, CA 92626
Tel:(714) 545-0100 / (800) 548-5100 Extension 2306
Fax:(714) 668-3149
E-Mail: sandyfl@earthlink.net
E-Mail: sperle@icnpharm.com
Personal Website: http://sandy-travels.com
ICN Worldwide Dosimetry Website: http://www.dosimetry.com
************************************************************************
You are currently subscribed to the Radsafe mailing list. To unsubscribe,
send an e-mail to Majordomo@list.vanderbilt.edu Put the text "unsubscribe
radsafe" (no quote marks) in the body of the e-mail, with no subject line.
You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/