[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Entergy Invests in Future at Arkansas Nuclear One



Index:



Entergy Invests in Future at Arkansas Nuclear One

British Energy slumps after reactor shutdown

N.Korea threatens to ditch nuclear freeze deal

CP&L's Robinson plant seeks 20-yr license renewal

Duke Power's Nuclear Stations Meet Customer Demand in Record Fashion

========================================



Entergy Invests in Future at Arkansas Nuclear One



RUSSELLVILLE, Ark., Aug. 13 /PRNewswire/ -- Entergy (NYSE:ETR) is 

investing in the future of Arkansas with its decision to replace both 

steam generators and the reactor vessel head for Arkansas Nuclear 

One's Unit 1. Replacement work is scheduled for fall 2005 during the 

unit's 19th refueling outage.



New steam generators will mean efficiency gains and improved 

equipment reliability going forward.  A new reactor vessel head will 

resolve Unit 1's potential susceptibility to the industry's generic 

Alloy 600 reliability issues.  Alloy 600, a nickel alloy, is a 

material commonly used on reactor vessel head nozzle penetrations. 

After years of prolonged exposure to elevated temperatures and 

pressure, Alloy 600 has shown a potential for cracking. Repairing 

such cracks can extend the duration of outages.



Steam generators are massive heat exchangers about 75 feet in length 

weighing over 500 tons located inside the reactor building. They 

create steam by transferring heat from water heated in the reactor to 

water in a secondary system.  The steam is used to spin the turbine-

generator to create electricity just as in fossil-fueled generating 

plants.



Both ANO Unit 2 steam generators were replaced in 2000. That was the 

largest project for the site since original construction.  Unit 2 was 

shut down for 85 days to complete the $150 million project.  Unit 2's 

reactor vessel head was inspected during this spring's refueling 

outage, and no evidence of cracking was found.



The estimated cost to build and install Unit 1's steam generators and 

vessel head is about $235 million.



ANO is a valuable emission-free generation asset for Entergy.  

Entergy Arkansas customers benefited from last year's record-setting 

production at the site.  Record efficiencies at ANO, combined with a 

general decrease in fuel costs and purchased power, resulted in a 

nearly 10 percent reduction on typical residential bills this year.  

ANO's increased production is due primarily to improvements in 

operational efficiency and equipment reliability and less downtime 

for refueling.  With 56 percent of Entergy Arkansas' power coming 

from Arkansas Nuclear One last year, the company spent less on more 

costly non-nuclear fuels and power purchased on the open market.



Unit 1, in commercial operation since 1974, is licensed to operate 

until 2034.  The Nuclear Regulatory Commission renewed its operating 

license in 2001, adding 20 years to an authorized 40-year initial 

operating period scheduled to end in 2014.

-------------------



British Energy slumps after reactor shutdown



LONDON, Aug 13 (Reuters) - British Energy Plc shares fell more than a 

third on Tuesday after the privatised nuclear power producer said it 

had taken another reactor out of service and was reviewing production 

forecasts after the unplanned shutdown.



It was the second 600 megawatt (MW) reactor taken out of service at 

Torness power station in Scotland, and the company, Britain's biggest 

electricity generator, said it was not clear when it would come back 

on stream.



Analysts said the difficulties would hit British Energy's profits and 

its dividend could be under threat.



The Torness Reactor 1 was taken out of service at midday on Monday to 

investigate vibrations on a gas circulator. Its twin, Torness Reactor 

2, has been out of action and under repair since mid-May, when a gas 

circulator failed.



British Energy has similar gas circulators at its Heysham 2 reactor 

in northwest England and those operations were continuing as normal, 

but were under review, it said.



The company's Dungeness nuclear power station in southeast England is 

also out of commission for repairs and maintenance after an 

unscheduled stoppage earlier this month.



"British Energy is quantifying the implications of the above for this 

year's generation forecast and a further statement will be made on 

this later today," it said.



At 1135 GMT, shares in the company were 37 percent lower at 56-1/4 

pence, valuing British Energy at about 370 million pounds. Earlier 

they hit 47 pence, their lowest since the company was privatised and 

floated on the stock market six years ago.



"The worry is that if the output is knocked, profits are going to be 

hit, and that endangers the dividend, which is already looking ropy," 

said Philip Hollobone, analyst at SG Securities.



The company paid a dividend of 16 pence in 1999, and halved it a year 

later, keeping it at eight pence since then.



"We're now potentially looking at them cutting it in half again," 

Hollobone said.



The company had expected to generate 67.5 terawatt hours (TWh) in the 

year 2002/03 and Hollobone said the difficulties could shave 2.5 TWh 

off that. "But we'll have to wait for their own figures," he added.



UNDERPERFORMER



News of the Torness outage had little effect on UK power prices and 

day ahead prompt power was trading at 11.65/11.70 pounds per megawatt 

hour, hovering around the opening level.



"Six hundred megawatts makes little difference in a market which is 

already over-supplied," one dealer said.



British Energy's shares have lost more than 80 percent of their value 

in the past year and before Tuesday's fall had already underperformed 

their British power sector peers by 34 percent over the same period.



The company has suffered as wholesale power prices fell 30 percent 

following the introduction of a more competitive market just over a 

year ago. It is the only significant British power generator with no 

access to retail customers through ownership of a national brand or a 

former regional monopoly.



British Energy shares often fluctuate sharply because analysts differ 

markedly over how to value the business, which has long-term 

decommissioning liabilities.



In May, it reported annual pre-tax profits of 47 million pounds, but 

that was before 500 million pounds of exceptional write-offs on 

generating assets and trading contracts associated with the wholesale 

power price slide.



Other British electricity generators have restored a retail customer 

base since the privatisation process separated the industry in the 

1990s. As a result they can offset wholesale losses with higher 

profits at the other end of the power chain.



But British Energy never achieved critical mass in the retail area, 

and now has no household end-user customers.

----------------



N.Korea threatens to ditch nuclear freeze deal



SEOUL, Aug 13 (Reuters) - North Korea rejected on Tuesday a U.S. 

demand to submit to nuclear inspections and threatened to pull out of 

a 1994 deal under which Pyongyang froze its atomic weapons programme 

in return for two reactors.



Last Wednesday, U.S. and other officials attended a concrete-pouring 

ceremony at the planned reactor site at Kumho, North Korea.



U.S. envoy Jack Pritchard said in a speech there the North should 

allow international checks on old atomic sites and plutonium stocks 

"now, not later."



The North Korean Foreign Ministry spokesman, in a statement issued by 

the official KCNA news agency, said the United States was to blame 

for years of delays to the project. Originally, the first reactor was 

to have been ready by 2003.



"The reality is pushing us to the phase where we should make a final 

decision to go our own way," the ministry spokesman said.



This was a reference to the core of the U.S.-North Korea deal which 

was brokered in 1994 after the peninsula came close to war.



The crux of the accord was to stop Pyongyang acquiring weapons-grade 

plutonium and give it light-water reactors which are harder to misuse 

than the North's Soviet-era models.



Pyongyang has made similar threats in the past, but the timing of 

Tuesday's comments was particularly sensitive as the two Koreas hold 

talks and Washington decides when to send an envoy to the North.



Washington has rejected previous compensation claims.



Under the 1994 accord, known as the Agreed Framework, a multinational 

consortium including the United States will deliver key components 

for the reactors only when the International Atomic Energy Agency has 

inspected the old sites and stocks.



The agency has said it needs to start that work now for the 

consortium to deliver the crucial parts on time. Washington has said 

the North caused delays by rejecting inspections.



North Korea argues there is no such deadline or requirement, and 

wants Washington to compensate it for lost energy.



"By delaying construction...the U.S. has caused a huge loss of 

electricity to the DPRK and created grave difficulties in its economy 

as a whole," the ministry spokesman said. "This has seriously 

threatened its right to existence."



The DPRK is the acronym for North Korea's official title, the 

Democratic People's Republic of Korea.



The spokesman said Washington should discuss compensation "whether it 

likes it or not" and save the deal by agreeing to 

simultaneous action rather than demanding early inspections.



"We will move if the U.S. does," he said, according to KCNA.

----------------



CP&L's Robinson plant seeks 20-yr license renewal



WASHINGTON, Aug 12 (Reuters) - Carolina Power & Light, a unit of 

Progress Energy Inc. <PGN.N>, has asked the Nuclear 

Regulatory Commission for a 20-year renewal of the operating license 

for the H.B. Robinson nuclear power plant Unit 2, the agency 

said on Monday.



The current license for the plant located near Hartsville, South 

Carolina expires in July 2010. The nuclear power plant began 

operating in 1970.



The NRC said in a statement that it launched a review of Carolina 

Power's June request. Any company or group seeking a hearing 

on the nuclear plant renewal application has until Aug. 18 to submit 

a request, the agency said.



The NRC set a tentative timetable, in which it aims to issue a 

commission decision on the license renewal in Dec. 2004.



The Robinson plant also has a coal-fired electricity generating unit.

-----------------



Duke Power's Nuclear Stations Meet Customer Demand in Record Fashion



CHARLOTTE, N.C., Aug. 12 /PRNewswire-FirstCall/ -- During a hot, 

humid summer in which electricity demand has been 

consistently high, Duke Power's nuclear stations have established a 

new reliability record.



The company's seven units in North Carolina and South Carolina have 

simultaneously operated for a record 86 consecutive days -- 

eclipsing the old record of 85 days set in the summer of 2000.



For the first half of 2002, nuclear generation has provided 60 

percent of Duke Power customers' electricity needs.  This is 

especially 

important because a four-year drought has seriously limited the 

availability of the company's hydroelectric generators.



"This is why Duke Power has advocated a diverse energy mix to meet 

people's electricity needs," said Michael S. Tuckman, 

executive vice president, nuclear generation.  "Our balance has 

enabled us to meet our customers' electricity demands without 

interruption."



Duke Power's nuclear fleet is amassing an enviable long-term 

performance record.  Back in May, Catawba unit 1 set a national 

record for shortest refueling/maintenance outage by an ice condenser 

plant -- 21 days, one hour.



Two months earlier, McGuire unit 2 set a station record for shortest 

refueling outage -- 32 days, six hours, 40 minutes.



In 2000, Oconee Nuclear Station operated all three of its units 

simultaneously for 179 consecutive days, which is a national record 

for a three-unit station, according to a review by the Nuclear Energy 

Institute.



And last year, Oconee unit 2 operated for a company-record 485 

consecutive days.



"What this proves is we're getting better in the efficiency and 

effectiveness of our refueling/maintenance outages, resulting in 

shorter outages and more reliable operation," Tuckman said.  "Our 

employees deserve much of the credit for their focus on safety, 

dedication and work ethic.



"The bottom line is our stations are available and generating low-

cost electricity when our customers need it most."



-------------------------------------------------

Sandy Perle

Director, Technical

ICN Worldwide Dosimetry Service

ICN Plaza, 3300 Hyland Avenue

Costa Mesa, CA 92626



Tel:(714) 545-0100 / (800) 548-5100  Extension 2306

Fax:(714) 668-3149



E-Mail: sandyfl@earthlink.net

E-Mail: sperle@icnpharm.com



Personal Website: http://sandy-travels.com/

ICN Worldwide Dosimetry Website: http://www.dosimetry.com/



************************************************************************

You are currently subscribed to the Radsafe mailing list. To unsubscribe,

send an e-mail to Majordomo@list.vanderbilt.edu  Put the text "unsubscribe

radsafe" (no quote marks) in the body of the e-mail, with no subject line.

You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/