Reply to note sent by Roman E. Fail:
We were tagged for the same offense. However, we were not allowed
the 10 day grace period. Our inspectors said 6 months, not 6 months
and 1 day. My solution is to ensure that they are done before the
magic 6 month date. So far I have been able to do it, but it may not
last. We are also an agreement state, and the requirement comes from
license restrictions and conditions. If others have another method,let
me know also.