[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
davis bessie messie details emerge
Raymond Shadis wrote:
> Thanks to Anne D Burt, Friends of the Coast, for sending this article
> on.
> FYI- More DETAILS EMERGE on DAVIS-BESSE. This is the first article
> I've seen where the reactor pressure vessel head material remaining
> at the base of the corroded hole is properly identified as, cladding.
> At Maine Yankee ( and it may be for Davis-Besse, as well) the interior
> of the reactor was coated with stainless steel by running bead after
> bead of stainless steel arc-weld around and around the inside surface
> of the vessel, like coil-made pottery, until the surface was covered
> with the requisite thickness (about 3/8". Each pass of the welder
> requires cleaning and inspection before the next pass so to insure
> that the bead is continuous, contains no bubbles or slag,has a surface
> free of slag, and is uniformly melted into the beads of weld below and
> along side of the new bead. There are thousands of opportunities to
> include and cover flaws. While such flaws provide starting places for
> tears, cracks, or corrosion, not-to-worry because cladding is not
> meant contain pressure and it may be that credit for the strength of
> cladding is not taken in pressure vessel analysis. However, with the
> pressure vessel gone, the "built-up" character of cladding must, it
> seems to me, says something about depending on the strength and
> durability ( including sensitization and stress corrosion cracking) of
> the remaining material- stainless stel or no, relatively small
> cross-section or no. Ray U.S. Questions Nuclear Plant's Repair Plan
> April 11, 2002
> By MATTHEW L. WALD
>
> BETHESDA, Md., April 10 - Officials from an Ohio nuclear
> power plant assured federal regulators today that they
> could repair corrosion that had eaten nearly all the way
> through a reactor lid, but faced a barrage of questions
> from the Nuclear Regulatory Commission staff.
> Executives of the Davis-Besse nuclear plant near Toledo met
> with commission officials to convince them that they could
> repair the hole by filling it with a 13-inch stainless
> steel disk, welded into place.
>
> After a three-hour meeting, the executives left with a long
> list of questions to answer, including how they would make
> sure that the heat of a welder's torch would not further
> damage the metal.
> Sixty-eight other reactors around the nation have a design
> similar to Davis-Besse's, and the commission is trying to
> determine if any of them have incurred the same kind of
> corrosion. All 68 have said they did not, but some did not
> provide enough of a basis for their assurances, said Ken
> Karwoski, a corrosion specialist with the commission.
> At Davis-Besse, which is owned by the FirstEnergy
> Corporation of Akron, Ohio, cooling water from the reactor
> leaked from nozzles on the reactor head; boric acid, which
> is mixed into the water to control the nuclear reaction,
> ate away about 70 pounds of metal, going through six inches
> of exterior steel.
> When the 25-year-old reactor was shut for refueling and
> repair of the nozzles this year, all that was left was a
> thin layer of steel meant to control corrosion inside the
> vessel.
> The regulators were shocked by the extent of the corrosion.
> Leaks were well known, but government and industry
> officials believed that when they occurred, the temperature
> at the vessel head, more than 600 degrees, would boil the
> water away and leave nothing but a harmless boron powder.
> After investigating, the commission staff concluded that
> the Davis-Besse operators had missed many opportunities to
> find the problem before it became so serious.
> Critics of nuclear power agreed.
> "When you're using a
> crowbar to knock the stuff off the reactor head, it's a
> sign you've gone too far," said David Lochbaum, a nuclear
> engineer with the Union of Concerned Scientists. Workers
> had pried boric acid off the head during a refueling
> shutdown in 2000.
> At the meeting today, about a dozen commission staff
> members asked about the "repair concept" that company
> officials presented.
> "It's a first-of-a-kind repair," said Brian W. Sheron,
> associate director for project licensing and technology
> assessment at the commission. "The staff is very concerned
> that whatever we approve, they are confident it is going to
> hold up."
> One issue, Mr. Sheron said, was "just the sheer size of the
> weld" - to hold in place a piece 13 inches in diameter and
> about 6 inches thick.
> FirstEnergy officials said the session had given them a
> clear indication of what information their plan would need
> to include to satisfy the commission. The company had hoped
> to submit that plan next week but company executives said
> after the session that it might take longer.
> If contractors cannot repair the vessel head, the company
> plans to replace it with the head from a reactor in
> Midland, Mich., that was abandoned during construction, or
> the head of a retired plant in Sacramento. They have also
> ordered a new reactor head, but do not expect delivery
> before February 2004.
> Delays are expensive because the plant employs 780 people,
> whether or not it generates electricity; property taxes
> alone run $500,000 a month. Officials hope to have the
> reactor running by summer.
> Opponents say that would be too soon. Christine
> Patronik-Holder, a spokeswoman for the Safe Energy
> Communication Council, said that until everyone agreed on
> exactly how the corrosion occurred, "plans to place patches
> amount to little more than Russian roulette with the lives
> of northern Ohioans."
> But the company is proceeding to figure out repair details,
> including how it will check for leaks when the work is
> completed.
> Radiation dosage in the repair area is so high that a
> welder would absorb in two hours as much radiation as the
> industry usually allows workers to incur in a year. In two
> and a half hours, the welder would reach the annual limit
> the commission sets. So the plan will rely on robot
> welders.
> Indeed, radiation in the affected area is so high that it
> will be a challenge just to X-ray the completed repairs to
> look for any flaws. Framatome, the French reactor company
> that will do much of the work, said it could compensate for
> the high background radiation.
>
> ttp://www.nytimes.com/2002/04/11/national/11NUKE.html?ex=1019720794&ei=1&en=9453952ea2027cca
--
Coalition for Peace and Justice and the UNPLUG Salem Campaign; 321 Barr
Ave., Linwood, NJ 08221; 609-601-8583 or 609-601-8537;
ncohen12@comcast.net UNPLUG SALEM WEBSITE:
http://www.unplugsalem.org/ COALITION FOR PEACE AND JUSTICE WEBSITE:
http://www.coalitionforpeaceandjustice.org The Coalition for Peace and
Justice is a chapter of Peace Action.
"First they ignore you; Then they laugh at you; Then they fight you;
Then you win. (Gandhi) "Why walk when you can fly?" (Mary Chapin
Carpenter)
************************************************************************
You are currently subscribed to the Radsafe mailing list. To unsubscribe,
send an e-mail to Majordomo@list.vanderbilt.edu Put the text "unsubscribe
radsafe" (no quote marks) in the body of the e-mail, with no subject line.
You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/