[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Davis Besse update from ANS







Bill Corcoran wrote:



>  UPDATED COST AND SCHEDULE ESTIMATES FOR DAVIS-BESSE were released on

> October 7 by the plant's operator, FirstEnergy Nuclear Operating

> Company

> (FENOC). The estimates, related to replacement work for the plant's

> degraded vessel head, remain "unchanged" from earlier cost figures of

> $55

> million to $75 million, according to FENOC. The cost for restoration

> work,

> however, is skyrocketing. Initially estimated at $50 million to $70

> million, this work, which FENOC said would "enhance the reliability

> and

> performance of plant equipment," now is expected to cost an additional

> $115

> million. Of the added cost, $65 million will be spent by year end,

> with the

> remaining $50 million to be incurred next year. Much of the $50

> million

> should be spent after the plant returns to service, which FENOC has

> pegged

> for the first quarter of 2003. The restoration work will include what

> FENOC

> called "extent of condition" projects, notably redesigning and

> rebuilding

> the containment sump, expanding work on air coolers, and a more

> extensive

> recoating of equipment and structures. The additional funds also will

> go

> toward "accelerated maintenance activities," FENOC said, such as

> reactor

> coolant pump work, cooling tower basin repairs, and valve maintenance.

>

> FENOC earlier had hoped to get the plant back on line by the end of

> the

> year, but, according to the company, the latest change in schedule "is

>

> designed to further ensure that related work is completed in

> accordance

> with all applicable requirements, with the continued understanding

> that

> restart is subject to NRC review and approval."

>    Davis-Besse, an 873-MWe (net) Babcock & Wilcox pressurized water

> reactor

> located in Oak Harbor, Ohio, has been shut down since February when

> the

> plant started a refueling outage. During the outage, severe

> degradation of

> the vessel head was discovered in March. FENOC has purchased a

> replacement

> head from the discontinued Midland nuclear power plant in Michigan,

> and is

> in the process of installing the replacement head. FENOC noted that

> "structure work to support replacement of the reactor head has been

> completed, all significant modifications are progressing on schedule,

> and

> all major work is expected to be finished by year-end."

>    FENOC has spent $20 million per month in July and August to buy

> replacement power, and another $10 million to $15 million per month

> for

> nonsummer months.

> * With repairs under way to replace the degraded vessel head at

> Davis-Besse, rust stains and what appeared to be boric acid deposits

> were

> found in mid-October on the exterior bottom of the vessel. FENOC was

> performing tests to identify the source of the stains. Viktoria

> Mitlyng,

> NRC spokesperson, said on October 21 that the stains, found near

> lower-vessel nozzle penetrations, are probably the result of one of

> two

> scenarios. Most likely, she said, the stains were caused by "wash down

> of

> boric acid from the top of the reactor during cleaning." A second,

> less likely possibility, she said, is that the stains were caused by

> "leakage

> from the bottom nozzles that are smaller but similar to the nozzles on

> the

> top" of the reactor. Fifty-two nozzles penetrate the bottom of the

> vessel,

> carrying instrumentation into the base of the vessel. This was the

> first

> time that FENOC workers had inspected the vessel bottom because it was

>

> covered with insulation prior to the inspection. Mitlyng said that

> FENOC

> was performing chemical analysis of the rust stains, and the NRC was

> waiting to see results of those tests before any regulatory action was

>

> taken. FENOC was expected to have test results during the week of

> October

> 21, according to Mitlyng.

> * The NRC on October 9 issued a 96-page "lessons learned" report

> looking

> into the agency's handling of the Davis-Besse vessel head degradation.

> The

> report, prepared by an NRC task force, concluded that while the

> degradation

> was preventable, it was allowed to occur because the NRC, Davis-Besse,

> and

> the nuclear industry failed to adequately review, assess, and follow

> up on

> relevant operating experience. Also, the report noted that Davis-Besse

>

> failed to assure that plant safety issues would receive appropriate

> attention, and that the NRC failed to integrate known or available

> information into its assessments of Davis-Besse's safety

> performance.

> * Ten Davis-Besse violations were highlighted in a report issued on

> October

> 2 by the NRC's Augmented Inspection Team (AIT). The team had

> investigated

> the plant's vessel head degradation and FENOC's compliance with

> regulations. The NRC said that the safety significance of the

> violations

> (and any possible enforcement actions) would be determined later. The

> team

> found that FENOC was responsible for:

>    1. Operating the reactor with leakage from the reactor cooling

> system

> through cracks in the control rod drive mechanism (CRDM) nozzles.

>    2. Failing on numerous occasions to thoroughly clean the continuing

>

> buildup of boric acid on the reactor vessel head, which eventually led

> to

> the corrosion of the head.

>    3. Failure to identify the cause of, and take appropriate

> corrective

> actions for, recurrent accumulations of boric acid on the fins of the

> containment air coolers, which resulted in reduced air flow through

> the

> coolers.

>    4. Failure to identify boric acid corrosion as the cause of the

> repeated

> clogging of radiation filters in the containment building and take

> appropriate corrective actions.

>    5. Failure to implement a modification to the service structure

> above

> the reactor vessel head for better access to inspect and clean the

> head and

> the CRDM nozzles.

>    6. Failure to follow the corrective action procedure and complete a

>

> prescribed corrective action for adverse trends in reactor cooling

> system

> leakage, thereby missing an opportunity to identify the nature of the

> leakage and find the growing cavity on the reactor vessel head.

>    7. Failure to establish an adequate boric acid control procedure,

> which

> contributed to the failure, over the years, to properly identify and

> evaluate the leaking CRDM nozzles and the expanding cavity in the

> reactor

> head.

>    8. Recurrent failures to follow the boric acid control procedures

> designed to prevent extensive boric acid corrosion, which resulted in

> the

> failure to remove boric acid deposits and inspect the metal base of

> the

> reactor head as directed by the procedure. 9. Failure to follow the

> plant's corrective action program, designed to

> properly identify the cause of a problem and devise and implement a

> solution, which contributed to FENOC's failure to recognize that a

> through-wall leak had developed in the CRDM nozzles.

>    10. Failure to provide complete and accurate information to the NRC

> and

> maintain internal documents necessary to diagnose and resolve problems

> at

> the plant. Completeness and accuracy of these documents may have

> provided

> an earlier alert to FENOC's staff and to the NRC about the problem

> with the

> CRDM nozzle leakage or may have caused the NRC to establish a

> different

> regulatory position on the urgency for inspecting the vessel head.

> * The NRC on October 16 announced that FENOC was at fault for allowing

> five

> workers to leave the Davis-Besse site in February while wearing

> radiologically contaminated clothing. Microscopic radioactive

> particles

> were later found in hotel rooms and homes in Ohio, Texas, South

> Carolina,

> and Virginia. There was no threat to the public, according to the NRC.

> The

> workers, who had been at Davis-Besse under contractor duties, had been

>

> performing tasks on the plant's steam generator. The steam generator

> work

> was not related to the vessel head degradation discovered at the plant

> in

> early March.

>    During a public meeting in Ohio on October 16, the NRC said that

> Davis-Besse did not properly assess how much radiation the workers

> were

> exposed to inside the steam generator. In that regard, the plant had

> failed

> to "conduct timely and suitable measurements of concentrations of

> radioactive material in air in work areas or of concentrations of

> radionuclides excreted from the body," thus compromising the ability

> to

> assess dose, the NRC noted. There also was a failure to adequately

> survey

> the workers prior to their release from the site. NRC officials at the

>

> public meeting said that the agency had not yet determined the

> significance

> of this incident and whether FENOC should be penalized for violating

> NRC

> regulations.

>    A report detailing the workers' exposure--along with separate

> reports on

> the Davis-Besse "lessons learned" (see second bulleted item above) and

> the

> AIT investigation (see third bulleted item)--are scheduled to be

> available

> on the NRC's Web site at

>

> www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation/news.

>

> html>.

>

>

> To unsubscribe from this group, send an email to:

> DBRVH_LTBL-unsubscribe@yahoogroups.com

>

>

>

> Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.



--

Coalition for Peace and Justice and the UNPLUG Salem Campaign; 321 Barr

Ave., Linwood, NJ 08221; 609-601-8583 or 609-601-8537;

ncohen12@comcast.net  UNPLUG SALEM WEBSITE:

http://www.unplugsalem.org/  COALITION FOR PEACE AND JUSTICE WEBSITE:

http://www.coalitionforpeaceandjustice.org   The Coalition for Peace and

Justice is a chapter of Peace Action.

"First they ignore you; Then they laugh at you; Then they fight you;

Then you win. (Gandhi) "Why walk when you can fly?"  (Mary Chapin

Carpenter)





************************************************************************

You are currently subscribed to the Radsafe mailing list. To unsubscribe,

send an e-mail to Majordomo@list.vanderbilt.edu  Put the text "unsubscribe

radsafe" (no quote marks) in the body of the e-mail, with no subject line.

You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/