[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

report questions NRC decisions on Davis Besse





>From the article::

"That finding - that the NRC let FirstEnergy's money concerns drive what



was supposed to be a safety decision - is one of the main conclusions in



a highly critical review by the agency's Office of Inspector General. "



Profits before safety. If it happened at DB, its probably happening at

your friendly neighborhood nuclear plant.



Norm





Report hits NRC decisions on Besse



01/03/03



John Funk and John Mangels

Plain Dealer Reporters



The Nuclear Regulatory Commission had enough evidence to justify

shutting down the Davis-Besse nuclear plant in late 2001 for safety

concerns, but the agency let the reactor keep running largely because it



didn't want to hurt owner FirstEnergy Corp. financially.



That finding - that the NRC let FirstEnergy's money concerns drive what

was supposed to be a safety decision - is one of the main conclusions in



a highly critical review by the agency's Office of Inspector General.



The document, obtained by

The Plain Dealer before its

public release, describes

numerous flaws,

misinterpretations,

inconsistencies and

unsupported conclusions in

how the NRC responded to

FirstEnergy's reluctance to

shut down by Dec. 31, 2001,

to inspect for suspected

cracks and leaks in its

reactor lid.



The agency struck a

compromise with the

company, allowing the

Toledo-area plant to continue making electricity until Feb. 16.



Three weeks later, inspection workers found not only cracks, but a

pineapple-size rust hole that breached the thick steel lid, caused by

the

corrosive leaking coolant.



It was the nation's closest brush with a major nuclear accident since

Three Mile Island in 1979.



The inspector general's report singles out the NRC's top reactor safety

official, Sam Collins, for his decision to let FirstEnergy delay the

inspection. It notes Collins had "strong justification" to order that

Davis-Besse cease operating, and that he had a promise from the

company's nuclear division president for a voluntary pre-Dec. 31

shutdown

if the NRC had lingering safety worries.



"The report is an illustration of how the NRC violated the public

trust," said

Rep. Dennis Kucinich. The Cleveland Democrat is a member of a

congressional committee that oversees the agency.



"FirstEnergy and the NRC worked together to put profits above public

safety. It's unacceptable," Kucinich said.



NRC Chairman Richard Meserve insisted yesterday that public safety, not

corporate concerns, had dictated the agency's approval of the inspection



delay.



"It's a nuanced issue," Meserve said of the need to strike a balance

between being a safety-minded regulator and an overly burdensome one.

"Safety in fact is our highest priority. We're fully prepared to issue

[shutdown] orders if we think it's necessary to protect public safety. I

don't

want to necessarily disagree with the inspector general. You're faced

with

a situation where you had some uncertainty about conditions in the

plant."



NRC staff members and managers made the right decision, based on the

information they had at the time, he said. Meserve promised to respond

to

the report's findings within 90 days. Collins could not be reached for

comment.



While the inspector general stopped short of saying the agency made the

wrong decision, the report finds fault with much of the decision-making

process:



The NRC gave undue consideration to its decision's impact on FirstEnergy



and the nuclear industry. The agency's regulations allow its staff to

take

into account the financial costs of any order; however, the Inspector

General concluded that the inspection delay went against the NRC's goal

of making sure reactors like Davis-Besse at high risk for lid cracking

were

quickly checked.



The company wanted to shut down March 31, when it had already

arranged for the people and equipment to do the special inspection as

well

as a planned reactor refueling. To halt production earlier would not

only be

costly but might cause power shortages in northwest Ohio, FirstEnergy

officials told the NRC.



NRC managers and staff members seemed to buy the argument.



"It would clearly be punitive to shut a plant down and they sit there

for a

month waiting to obtain the correct inspection equipment," one senior

manager e-mailed another in a message cited in the report.



The NRC "informally established an unreasonably high burden" of needing

absolute proof of a safety problem to justify issuing a shutdown order.

The

problem with that logic, the report noted, was that the only way to get

such proof was to order a shutdown for inspection.



The agency had enough evidence to conclude that Davis-Besse's lid was

cracked and leaking, the report said. FirstEnergy's own estimates were

that between one and nine metal sleeves on the lid were leaking.



Investigators found that the agency is reluctant to risk a legal battle

over a

shutdown order unless it has a "guaranteed win."



Moreover, an order was unnecessary, because Bob Saunders, president

of FirstEnergy's nuclear division, had promised Collins that Davis-Besse



would shut down without opposition if the NRC determined that it was

necessary.



The Union of Concerned Scientists, a watchdog group whose complaint

about the NRC's Davis-Besse decision launched the inspector general's

investigation, said its findings demonstrate the need for reform at the

agency.



While FirstEnergy has made many management changes in the wake of

the rust hole debacle, the NRC has made none, said the group's David

Lochbaum, a nuclear safety engineer.



"They need to bring people in from the outside who aren't of the same

mind-set and will bring fresh perspective and don't have baggage," he

said.



To reach these Plain Dealer reporters:



jfunk@plaind.com, 216-999-4138



jmangels@plaind.com, 216-999-4842





© 2003 The Plain Dealer. Used with permission.

--

Coalition for Peace and Justice and the UNPLUG Salem Campaign; 321 Barr

Ave., Linwood, NJ 08221; 609-601-8583 or 609-601-8537;

ncohen12@comcast.net  UNPLUG SALEM WEBSITE:

http://www.unplugsalem.org/  COALITION FOR PEACE AND JUSTICE WEBSITE:

http://www.coalitionforpeaceandjustice.org   The Coalition for Peace and

Justice is a chapter of Peace Action.

"First they ignore you; Then they laugh at you; Then they fight you;

Then you win. (Gandhi) "Why walk when you can fly?"  (Mary Chapin

Carpenter)





************************************************************************

You are currently subscribed to the Radsafe mailing list. To unsubscribe,

send an e-mail to Majordomo@list.vanderbilt.edu  Put the text "unsubscribe

radsafe" (no quote marks) in the body of the e-mail, with no subject line.

You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/