[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
"Slow going on MAPLE"
A while back someone asked about progress at the MAPLE project at Chalk
River Laboratories.
Here's the latest public info on that.
Jaro
http://www.cns-snc.ca/branches/quebec/quebec_main.html
^^^^^^^^^^^^^^^^^^^^^
http://www.magma.ca/~drcanrt/mapleslow.htm
Slow going on MAPLE
by Terry Myers
The North Renfrew Times, October 8, 2003
Atomic Energy of Canada Ltd. is still trying to figure out what went wrong
in tests of the new MAPLE 1 reactor at the Chalk River Laboratories.
Company officials told the Canadian Nuclear Safety Commission (CNSC)
recently that they are still trying to find out why the reactor did not
operate the way it was designed to.
Jean-Pierre Labrie, general manager of the MAPLE reactor project, said AECL
is still working on its computer simulations.
"We have had to go to more sophisticated computer codes to analyze the
behaviour we have seen from our commissioning results and we are still in
the middle of these calculations," he said.
"These are very complex and time consuming in terms of computer time
calculations.
"They are multi-calculations with particle simulations, so they take a long
time to run."
The MAPLE 1 reactor at Chalk River was placed in a "secure shutdown state"
in June after tests showed the reactor operating with a "positive power
coefficient."
The MAPLE reactor is designed to operate with a negative coefficient.
In rough terms, a reactor with a negative coefficient will gradually slow to
a stop if safety systems fail and there is no one at the controls.
A reactor with a positive coefficient would instead run faster and hotter
until it reaches the point of a meltdown.
In a report to members of the safety commission, Barclay Howden, the acting
director general of nuclear facilities regulation for the CNSC, said the
positive reading for MAPLE 1 was "contrary to the (reactor's) core design
characteristic" and "could have a negative impact on safety."
However, officials from AECL told the CNSC in July that they expect the
finding to have no effect on the reactor's "safety case."
In fact, they said the power coefficient - a combination of several
competing factors - may even fall to zero or become negative when the
reactor reaches full power.
Gary Kugler, vice-president of nuclear products and services for AECL, said
the company had expected to find a small negative result, but instead came
up with a small positive finding.
"Had we predicted a larger and negative coefficient and found in the
experiment a smaller negative coefficient, it probably would not have become
an issue at all," he said.
"But the fact that it went from slightly negative to slightly positive
certainly does require an explanation...
"So we are certainly looking into this very carefully. We need to understand
it."
Howden told the commission members he expects to receive AECL's final
reports on the issue by the end of October.
Low power
While AECL is still analyzing the commissioning results, work on the two
MAPLE reactors being built at Chalk River is moving forward slowly.
The CNSC has given AECL permission to start up the MAPLE 1 again and run it
at low power so the company can continue to test the reactor's shut-off
systems.
AECL has also begun commissioning the MAPLE 2 reactor.
The reactor was loaded with fuel and was expected to begin "the final
approach to critical" last week.
AECL is building the two 10-megawatt MAPLE reactors and a new isotope
processing facility (NPF) at Chalk River under contract with MDS Nordion.
Once complete, the MAPLE facilities will produce medical isotopes like
Molybdenum-99 that Nordion markets around the world, a job now done at the
NRU reactor.
The MAPLE project fell about two years behind after problems with the
shut-off rods, one of the reactor's emergency safety systems, were
discovered in July 2000.
Earlier this year, AECL announced new target dates for the completion of the
project.
AECL said it hoped to have MAPLE 1 declared "in service" as of September 19,
while the target for MAPLE 2 was December 19.
-------------------------------
************************************************************************
You are currently subscribed to the Radsafe mailing list. To unsubscribe,
send an e-mail to Majordomo@list.vanderbilt.edu Put the text "unsubscribe
radsafe" (no quote marks) in the body of the e-mail, with no subject line.
You can view the Radsafe archives at http://www.vanderbilt.edu/radsafe/