[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Agencies seek grand jury documents on former nuke site
Index:
Agencies seek grand jury documents on former nuke site
Japan Atomic Power missed pipe inspections until 2001
Mitsubishi Heavy used notebooks to keep track of nuclear
Audit: Plutonium Program Behind Schedule
-------------------------------------------------------------------
Agencies seek grand jury documents on former nuke site
Aug 20 (CNN) State and federal agencies want to see the sealed files 
of a grand jury that investigated alleged environmental crimes at the 
former Rocky Flats nuclear weapons plant after an advocacy group said 
cleanup plans for the site were dangerously incomplete.
The federal Environmental Protection Agency, U.S. Department of 
Energy and Colorado Department of Public Health and Environment 
requested or planned to request the files from U.S. Attorney John 
Suthers, spokesmen for the agencies said Thursday.
U.S. attorney's spokesman Jeff Dorschner said Suthers has received at 
least one of the requests, but he did not know when Suthers would 
respond. A court order would be required for Suthers to release the 
documents.
The request came a day after an FBI agent who led a 1989 raid at 
Rocky Flats warned against plans to turn the site, about 10 miles 
west of downtown Denver, Colorado, into a wildlife refuge, saying it 
would be too dangerous.
Agent Jon Lipsky said he had been ordered by superiors not to comment 
on his investigation, but said concerns raised by the advocacy group, 
the Ambushed Grand Jury Citizens' Investigation, were valid.
He had appeared at a Wednesday news conference, where Jacque Brever, 
a member of the advocacy group and a former Rocky Flats employee, 
released a report accusing federal officials of lying about the 
extent of contamination at the site.
Brever's report said so much radioactive waste was disposed of 
clandestinely at Rocky Flats that some contaminated areas are not 
part of the cleanup.
"I am happy that we are the catalyst and hope they will not certify 
the site as clean until they have gone back and looked at the areas 
we have pointed out to them," said Caron Balkany, co-author of a book 
compiled by the group, "The Ambushed Grand Jury."
Rocky Flats made plutonium triggers for nuclear weapons until 
production was shut down after the 1989 FBI raid. A federal grand 
jury investigated allegations of safety violations by the contractor 
and the Department of Energy.
The grand jury wanted to issue eight indictments, including two 
against corporations, but the Justice Department declined. The grand 
jury's report and investigative files remain sealed.
One of the plant's operators at the time, Rockwell International 
Corp., pleaded guilty to 10 hazardous waste and clean water 
violations in 1992 and paid an $18.5 million fine.
The Department of Energy plans to convert the site into a wildlife 
refuge after a $7 billion cleanup is complete.
-----------------
Japan Atomic Power missed pipe inspections until 2001
OSAKA, Aug. 21 (Kyodo) - Japan Atomic Power Co. did not carry out 
inspections of a section of pipe at one of its nuclear power plants 
in Fukui prefecture until 2001, when it inspected a point 
corresponding to the section of pipe that caused the country's 
deadliest nuclear plant accident on Aug. 9 in another nuclear plant, 
company officials said.
Japan Atomic Power conducted inspections at the point on the pipe at 
the No. 2 reactor of the Tsuruga Nuclear Power Plant for the first 
time in 2001 after Mitsubishi Heavy Industries Ltd., which had 
conducted inspections of the reactor, notified its operator of the 
need for further inspections, the officials said.
The company, owned chiefly by the nation's nine electric utilities, 
builds and operates nuclear power plants. It started operations of 
the reactor at the Tsuruga plant in February 1987.
At the inspections conducted in 2001, Japan Atomic Power concluded 
that the pipe could be used for about four more years, they said.
The company plans to replace the pipe in December this year during 
regular inspections, according to the officials.
Four workers were killed and seven others injured by superheated 
steam that burst from a ruptured coolant water pipe at Kansai 
Electric Power Co.'s No. 3 reactor at the Mihama Nuclear
-----------------
Mitsubishi Heavy used notebooks to keep track of nuclear
OSAKA, Aug. 21 (Kyodo) - Mitsubishi Heavy Industries Ltd. kept track 
of nuclear inspections in notebooks when it was first assigned to 
inspect the Mihama Nuclear Power Plant in Fukui Prefecture in 1989, 
informed sources said Saturday.
The coolant water pipe of Mihama's No. 3 reactor -- the cause of 
Japan's deadliest nuclear accident earlier this month -- was missing 
from the list of inspection items, the sources said.
Mitsubishi Heavy says it is looking into why the pipe was missing 
from the list.
On Aug. 9, four workers were killed and seven others injured when 
superheated steam burst from a ruptured coolant water pipe of the 
reactor operated by Kansai Electric Power Co.
According to Mitsubishi Heavy and other sources, the company kept 
track of about 6,000 inspection items using notebooks for about six 
years through 1994, when it computerized the record-keeping system.
Mitsubishi Heavy created the notebook-based inspection system in 1989 
at the request of KEPCO, three years after an accident at the Surrey 
nuclear power plant in the United States, which also involved a 
ruptured pipe.
In 1996, Mitsubishi Heavy handed the notebooks over to Osaka-based 
Nihon Arm Co., which took over the inspection work, the sources said.
Nihon Arm said it computerized the information in the notebooks on 
its own so it could easily collate drawings of pipes and other parts 
of the reactors with the list of inspection items.
Nihon Arm said one of its veteran engineers discovered that the part 
of the coolant water pipe involved in the accident was missing from 
the inspection items while inspecting the power plant in April 2003.
Nihon Arm said it notified KEPCO of the finding, but KEPCO said it 
was unaware of the omission until the accident.
------------------
Audit: Plutonium Program Behind Schedule
WASHINGTON (AP) - A decade-old program to secure plutonium and other 
fissionable material at Los Alamos National Laboratory is years 
behind schedule, increasing the likelihood of accidents and workers' 
exposure to radiation, according to an Energy Department audit.
The program to "stabilize" fissionable material, including plutonium, 
at the government's weapons research lab in New Mexico was supposed 
to have been finished two years ago. But it now is targeted for 
completion in 2010, with its expected cost ballooning to at least 
$183 million, or 75 percent more than the original price tag.
The delays and failures to meet milestones outlined for the program 
have increased "the possibility that containers (of vulnerable 
radioactive materials) could leak and workers could be exposed to 
radiation resulting in serious health consequences," said the report 
by Gregory Friedman, the department's inspector general.
The report noted an incident at Los Alamos last August in which two 
workers were exposed to plutonium 238 while examining a degraded 
package of contaminated rags. The department fined the lab $770,000, 
but it won't have to pay because by law the lab manager, the 
University of California, is immune from such penalties as a 
department contractor.
While some progress has been made in recent years in repackaging and 
disposing of the radioactive material at Los Alamos, "stabilization 
has not been accelerated to the level anticipated," Friedman wrote. 
He cited a failure to fully fund the program and management 
shortcomings.
Unless the effort is given a higher priority "radioactive materials 
at the laboratory may continue to deteriorate and negatively impact 
the safety and health of workers," Friedman wrote Energy Secretary 
Spencer Abraham in a letter dated Aug. 16 and made public Thursday.
Many of the inspector general's concerns mirror issues raised by the 
Defense Nuclear Facilities Safety Board, an independent advisory 
panel, in a letter to Abraham last February.
The board urged the department to speed up its processing and 
repackaging of thousands of items containing fissionable or 
radioactive materials- many of them left over from Cold War-era 
nuclear research.
The accident last August "should have reinforced the urgency" of the 
task at hand, yet neither the department nor Los Alamos officials 
have demonstrated "an appropriate sense of urgency" about addressing 
the total inventory of radioactive and fissionable materials at the 
site, said the advisory group.
Its report said that of 5,718 items in need of attention, 1,403 have 
been dealt with as of Sept. 31, 2003. They include radiation-
contaminated rags, non-weapons grade plutonium oxides, steel drums of 
uranium-tainted materials, and items simply labeled "excess material" 
from weapons-related work, but which are viewed as low risk.
And even more items have yet to be inventoried, according to the 
inspector general's findings and the advisory board. At least 155 
additional containers not considered in the stabilization plans have 
since been found, auditors said.
Responding to the inspector general's report, Michael Kane, an 
associate administrator at the National Nuclear Security 
Administration, said he "generally agrees" with the inspector 
general's findings. NNSA is responsible for the Energy Department's 
nuclear programs,
"While the auditors are correct the laboratory is behind schedule in 
some areas, they have exceeded scheduled expectations in other 
areas," Kane wrote in a letter formally replying to the report.
Kane also said that while the program has been underfunded in the 
past by as much as 40 percent in the late 1990s - funding has 
increased each year since 2001 and full funding is anticipated 
beginning in 2006.
Kevin Roark, a spokesman at the Los Alamos National Laboratory, 
referred questions about the inspector general's report to the NNSA. 
"The report speaks for itself," he said.
The Energy Department in 1995 ordered nuclear facilities including 
Los Alamos to better secure their fissionable and radiaoctive 
materials from Cold War-era activities. It directed the job be 
completed by 2002, a deadline that was later extended to 2005 and 
more recently to 2010.
-------------------------------------
Sandy Perle 
Senior Vice President, Technical Operations 
Global Dosimetry Solutions, Inc. 
3300 Hyland Avenue 
Costa Mesa, CA 92626 
Tel: (714) 545-0100 / (800) 548-5100  Extension 2306 
Fax:(714) 668-3149 
Global Dosimetry Website: http://www.dosimetry.com/ 
Personal Website: http://sandy-travels.com/ 
************************************************************************
You are currently subscribed to the Radsafe mailing list. To
unsubscribe, send an e-mail to Majordomo@list.vanderbilt.edu  Put the
text "unsubscribe radsafe" (no quote marks) in the body of the e-mail,
with no subject line. You can view the Radsafe archives at
http://www.vanderbilt.edu/radsafe/