At 03:26 PM 8/12/97 -0500, you wrote:
> I am trying to find if 10 CFR contains any regulations on how long
> personnel can work in a nuclear safety capacity. I have some numbers,
> but cannot find the regulatory reference. The numbers I have are:
>
> No more than 13 consecutive hours
> No more than 72 hours in any consecutive 7 day period
> No more than 24 hours in any consecutive 48 hour period
> No more than 16 hours in any consecutive 24 hours period
>
> I have a possible reference of a NRC Guidance Letter 8212.
>
> Can anybody help match these restrictions to a 10 CFR or other
> regulatory document?
>
> Send responses to DEAN.STEWART@RFETS.GOV
>
This is generally addressed in the Administrative Controls section of
the Technical Specifications for nuclear power plants, and is germaine
to workers in defined safety related functions. There is nothing in the
CFR that addresses this issue for the industry as a whole, to the best of
my awareness. I have copied an example of such admin controls below from
the CE Improved Standard Technical Specifications (NUREG-1432). The
wording is different than plants with the older Tech Spec format, but the
intent is the same. Generic Letter 82-12 issued the requirements for these
controls, and may be seen in its entirety at
ftp://ftp.fedworld.gov/pub/nrc-gc/gl82012.txt
Excerpts from the GL 82-12 are also provided to help out.
Best regards
=========================================================================
Excerpt NUREG-1432
"5.2.2.e
Administrative procedures shall be developed and implemented to limit the
working hours of unit staff who perform safety related functions (e.g.,
licensed SROs, licensed ROs, health physicists, auxiliary operators, and
key maintenance personnel).
Adequate shift coverage shall be maintained without routine heavy
use of overtime. The objective shall be to have operating personnel work
an [8 or
12] hour day, nominal 40 hour week while the unit is operating. However,
in the
event that unforeseen problems require substantial amounts of overtime to
be used,
or during extended periods of shutdown for refueling, major maintenance, or
major plant modification, on a temporary basis the following guidelines
shall be followed:
1. An individual should not be permitted to work more than
16 hours straight, excluding shift turnover time;
2. An individual should not be permitted to work more than
16 hours in any 24 hour period, nor more than 24 hours in any 48 hour
period,
nor more than 72 hours in any 7 day period, all excluding shift turnover time;
3. A break of at least 8 hours should be allowed between
work periods, including shift turnover time;
4. Except during extended shutdown periods, the use of
overtime should be considered on an individual
basis and not for the entire
staff on a shift.
Any deviation from the above guidelines shall be authorized in
advance by the [Plant Superintendent] or his designee, in accordance with
approved
administrative procedures, or by higher levels of management, in accordance
with
established procedures and with documentation of the basis for granting the
deviation.
Controls shall be included in the procedures such that individual
overtime shall be reviewed monthly by the [Plant Superintendent] or his
designee to
ensure that excessive hours have not been assigned. Routine deviation from
the above
guidelines is not authorized.
OR
The amount of overtime worked by unit staff members performing safety
related functions shall be limited and controlled in accordance with the
NRC Policy
Statement on working hours (Generic Letter 82-12).
============================================================================
========
Excerpts from GL 82-12
" June 15, 1982
TO ALL LICENSEES OF OPERATING PLANTS, APPLICANTS FOR AN OPERATING LICENSE,
AND HOLDERS OF CONSTRUCTION PERMITS "
..................
"The objective of the controls would be to assure that, to the extent
practicable, personnel are not assigned to shift duties while in a fatigued
condition that could significantly reduce their mental alertness or their
decision making capability. The controls shall apply to the plant staff who
perform safety-related functions (e.g., senior reactor operators, reactor
operators, health physicists, auxiliary operators, and key maintenance
personnel).
Enough plant operating personnel should be employed to maintain adequate
shift coverage without routine heavy use of overtime. The objective is to
have operating personnel work a normal 8-hour day, 40-hour week while the
plant is operating. However, in the event that unforeseen problems require
substantial amounts of overtime to be used, or during extended periods of
shutdown for refueling, major maintenance or major plant modifications, on a
temporary basis, the following guidelines shall be followed:
a. An individual should not be permitted to work more than 16 hours
straight (excluding shift turnover time).
b. An individual should not be permitted to work more than 16 hours in any
24-hour period, nor more than 24 hours in any 48-hour period, nor more
than 72 hours in any seven day period (all excluding shift turnover
time).
c. A break of at least eight hours should be allowed between work periods
(including shift turnover time).
d. Except during extended shutdown periods, the use of overtime should be
considered on an individual basis and not for the entire staff on a
shift.
Recognizing that very unusual circumstances may arise requiring deviation
from the above guidelines, such deviation shall be authorized by the plant
manager or his deputy, or higher levels of management. The paramount
consideration in such authorization shall be that significant reductions in
the effectiveness of operating personnel would be highly unlikely.
In addition, procedures are encouraged that would allow licensed operators
controls to be periodically relieved and assigned to other duties away from
control board during their tour of duty."
========================================================================
Judd M. Sills, CHP | Office: (619)455-2049
General Atomics, Room 01-166C| Fax: (619)455-3181
3550 General Atomics Court | E-Mail: sillsj@gat.com
San Diego, CA 92121 |