[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: MANAGEMENT APPROVAL OF RWP'S



At Salem Station, the Nuclear Shift Supervisor is not required to 
approve RWPs.  First line RP supervision approves all RWPs except for 
those involving entries into a Seal Table Room or Reactor Sump.  
These must be approved by the RPM (potential VHRAs).  In addition, 
the Nuclear Shift Supervisor must approve issuance of keys to these 
areas because he is supposed to be cognizant of the location of the 
in core detectors and thimbles.

If you have any other questions, contact the Duty RP Supervisor at 
(609)339-2608 or me at (609)339-2635.

Dave Ruyter
Dave Ruyter

dama@waterw.com