[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Re: TMI root causes -Reply
> I really think that the major difference between a SALP 1 plant and having the keys
> taken away is the SAFETY CULTURE that management encourages, and the worker bees
> just do out of well-taught habitual thinking patterns.
One of the problems you pose here is one of economics. Back in the
80's, a utility expended a significant number of $$ to attain and
then maintain a SALP 1 rating, as well as an INPO level 1 plant
rating. Now, utility management has come to the conclusion that the
extra $$ that are needed to maintain SALP 1 levels is unwarranted in
the "electricity competition" world. The decision by most is to spend
less, and be satisfied with the SALP 2 Level.
> On the one hand you've got, say,
> Clinton, where the plant manager refused to let the operators shut down when
> recirc pump leakage exceeded specs, because "the grid needs power". Contrast
> that to Monticello, shut down in the middle of the peak load season to fix an
> ECCS concern that they could have (maybe) pencil-whipped until the next
> refuel.
The above statement does not take into the account risk versus
benefit. You imply that NOT shutting down is a serious issue. One
could consider that shutting down to fix a problem that for all
practical purposes, could have been fixed later, and, without risk to
people or the environment. While the above is your example, this
could be said for many problems worked every day within a nuclear
utility. The fact that a spec was exceeded does not mean that there
is any serious consequence. Now, let's assume that the unit did not
shutdown. What would that shutdown have done to the grid? Would the
shutdown have placed a larger strain on the grid, causing unnecessary
problems to the majority of homes requiring that power? What time of
the year was it? These are all factors that you are second-guessing.
As far as the ECCS problem, as you said, it could have, perhaps, been
taken care of during the next shutdown. I guess what I am saying is,
that one need not shutdown immediately, for every individual problem
faced on a daily basis. To do that could cause serious repercussions,
both financially, and, to the expectation of the customers, i.e., to
have reliable and available power. each item must be assessed on its
own merits, and that is where good, knowledgeable and positive
management is required.
> Process controls and systems are futile if they are routinely blown off in the
> name of expediency or the almighty buck. Sometimes short-sighted (or
> technically incompetent) managers make decisions based on short-term economic
> pressures, compromising safety. I certainly cannnot speak definitively on
> this, but it is my humble impression that the NRC looks very closely at the
> culture of a plant's management and workforce during an inspection.
They damn well do!!!! Just look at all of the management changes
taking place in the industry. I believe that more than a dozen large
utilities have changed out the top management. The NRC DOES do a good
job in this area. Now I am not here to defend the NRC, but having sat
in on many NRC inspection meetings and exits, culture and management
is a key factor that they do look at. I had seen management in my
previous company changed out due to "NRC concerns" ...
Charles has seen a lot out there. That is one of the benefits of a
"road warrior" .... Observations are important. One of the problems
with the US nuclear industry is ... that we fail to learn from one
and other. Yes, there are industry meetings, such as ALARA PWR and
BWR Committees. But I found most of them to be all show without much
substance. NOT because the workers didn't care, or attempt to bring
back the knowledge gained, but because management (see, I am using
that key element again) .. refused to incorporate the lessons
learned. To grow, one must incorporate the good things from others,
institutionalize the good, and standardize. We haven't done much of
this. The Europeans do, for the most part. And, an added benefit of
standaradization is, cost effectiveness.
------------------
Sandy Perle
Technical Director
ICN Dosimetry Division
Costa Mesa, CA 92626
Office: (800) 548-5100 x2306
Fax: (714) 668-3149
sandyfl@earthlink.net
sperle@icnpharm.com
Personal Website: http://www.geocities.com/CapeCanaveral/1205
ICN Dosimetry Website: http://www.dosimetry.com
"The object of opening the mind, as of opening
the mouth, is to close it again on something solid"
- G. K. Chesterton -