Re: Clarification to D&D for Plutonium Areas



I was asked to clarify that this is for existing facilities which are to be
D&D'd.  This conceputual plan is to to provide enough information for
obtaining a cost estimate to actual do the work at a later date.  The
details for estimate can be plus or minus 30%.  I need to ID a plan to do
the work for the future design of D&D.

I hope this helps

Kirk Russell
krr@if.scientech.com

>Kirk Russell writes:
>
>>I have been tasked with conducting a conceptual design plan with ultimate
>>decontamination and decommissioning of two faciliites.
>
>Please clarify for us radsafers, do you mean you are designing a new
>facility and are only including a D&D *plan* in the design for a long time
>in the future?  Or do you mean an existing facility needs D&D *now* so that
>your planned facility can be constructed in/on the location of the now-hot
>areas?
>
>Thanks,
>Albert Lee Vest          The Ohio State University
>Health Physicist                 B-042 Graves Hall
>(614)292-0122                 333 West 10th Avenue
>                                 Columbus OH 43210
>My employer did not review or approve this message.